STEP 3<br />
NOTE THE SEVEN-INCH DISTANCE<br />
FROM THE EAVE OF THE BIN TO THE<br />
CENTER LINE OF THE HOLES IN THE<br />
TRACK. Bins with steeply-pitched roofs<br />
may allow the 7" distance to be reduced.<br />
Roofs with the low or “flat” profiles may<br />
require more clearance. Reinforcements<br />
for the roof or inner ladders which might<br />
interfere with the movement of the <strong>Stir</strong>-<strong>Ator</strong><br />
should be trimmed off as indicated in<br />
Drawing A on page 33. If this cannot be<br />
done, the 7" distance from the eave to the<br />
bolt holes must be incresed<br />
proportionately.<br />
STEP 4<br />
There should be slightly more track<br />
material than is required. Upon making the<br />
complete circuit of the bin, the end of the<br />
last section should be cut off so as to fit<br />
snugly against the forward end of the first<br />
length and a 7/16" hole drilled, 5/8" from<br />
the cut-off end. ALL TRACK JOINTS<br />
SHOULD BE ALIGNED AS SMOOTHLY<br />
AS POSSIBLE. Mis-alignment should be<br />
corrected by filing or bending, if necessary.<br />
STEP 5<br />
Because the <strong>Stir</strong>-<strong>Ator</strong> augers run very<br />
close to the bin wall, INSIDE WALL<br />
LADDERS MUST BE MOUNTED VERY<br />
CLOSE TO THE BIN WALL. If this cannot<br />
be accomplished, the ladder must be<br />
removed. A portable ladder is advised, and<br />
this can be obtained form your dealer. If<br />
the walk in door protrudes over 2-1/2" into<br />
the bin itself, SKID PLATES SHOULD BE<br />
PUT ON THE DOOR so that the augers<br />
will not get caught during <strong>Stir</strong>-<strong>Ator</strong><br />
operation.<br />
Photo 1<br />
STEP 6<br />
At this time, hook the three suspension chain hooks over the<br />
top edge of the fill hole. Space them equally around the fill<br />
hole. See Drawing B on page 36 or Photo 1.<br />
STEP 7<br />
Install the switch box above the inspection hole. Be sure the<br />
<strong>Red</strong> <strong>Giant</strong> will not hit it, and do not forget the brace. See Photo<br />
1 or Drawing A on page 33.<br />
Lead-in cord and shut-off chain need to be positioned so that<br />
the <strong>Stir</strong>-<strong>Ator</strong> will not catch them as it rotates around the bin.<br />
NOTE THE CLEARANCE REQUIREMENTS IN<br />
DRAWING A AND B.<br />
14 PNEG-1358 <strong>Red</strong> <strong>Giant</strong> <strong>Stir</strong>-<strong>Ator</strong>