START-UP 6START-UP SEQUENCE√Start-up sequence—unit power supply ON1 compressor crankcase resistances in operation from at least 8 hours2 no-load voltage measure3 phase sequence check4 pump manual start-up and flow check5 ON unit6 load voltage measure and absorptions7 check of the liquid light (no bouble)8 measure of the supply and return water temperature9 measure of the super-heating and sub-cooling10 check that no anomalous vibrations are present11 set-point personalization12 unit documentation available17