8. Submit to <strong>the</strong> Project Manager all shop drawings, samples and schedules<br />
sufficiently in advance <strong>of</strong> construction requirements to provide no less than thirty<br />
(30) calendar days <strong>for</strong> checking, and appropriate action;<br />
8. List exceptions to <strong>the</strong> Design Criteria taken by <strong>the</strong> Design-Build Firm in <strong>the</strong><br />
letter <strong>of</strong> Shop Drawing Transmittal to <strong>the</strong> Project Manager.<br />
CITY'S RESPONSIBILITY - <strong>the</strong> <strong>City</strong> will:<br />
1. Review shop drawings, data, and samples submitted by <strong>the</strong> Design-Build Firm<br />
to interpret <strong>the</strong> work depicted on such Submittal to be in general con<strong>for</strong>mance<br />
with <strong>the</strong> <strong>design</strong> concept and in general compliance with <strong>the</strong> Contract<br />
requirements. The <strong>City</strong>‟s review and comments, if any, constitutes a limited,<br />
conditional or qualified permission to use such materials, equipment or methods<br />
and does not constitute an acceptance <strong>of</strong> dimensions, quantities, details <strong>of</strong> <strong>the</strong><br />
material, equipment, device or item submitted.<br />
2. Review and return shop drawing submittals within 30 calendar days <strong>of</strong> receipt.<br />
3. Reject and return shop drawings to <strong>the</strong> Design-Build Firm without action<br />
(Stamped “REJECTED”) or review with <strong>the</strong> following applicable notation:<br />
a. "Design-Build Firm‟s Stamp required - Incomplete Review by Design-Build<br />
Firm ", or<br />
b. "Submittal Incomplete - See<br />
c. "Contract Variation Not Noted in Transmittal".<br />
SUBMITTAL PROCEDURES:<br />
Preliminary Shop Drawing Data: Within 20 days after <strong>the</strong> Award <strong>of</strong> <strong>the</strong> Contract <strong>the</strong><br />
Design-Build Firm shall submit to <strong>the</strong> Project Manager a complete listing <strong>of</strong><br />
manufacturers <strong>for</strong> all items <strong>for</strong> which shop drawings are to be submitted.<br />
Shop Drawing Submittal Schedule: Within 30 days after <strong>the</strong> Notice to Proceed, <strong>the</strong><br />
Design-Build Firm shall submit to <strong>the</strong> Project Manager a complete schedule <strong>of</strong> shop<br />
drawing submittals fixing <strong>the</strong> respective dates <strong>for</strong> submission, <strong>the</strong> beginning <strong>of</strong><br />
manufacture, testing, and installation <strong>of</strong> materials, supplies and equipment, noting those<br />
submittals critical to <strong>the</strong> progress schedule.<br />
Submittal Log: An accurate updated log <strong>of</strong> submittals maintained by <strong>the</strong> Design-Build<br />
Firm and subject to review by <strong>the</strong> <strong>City</strong> at each scheduled progress meeting.<br />
When reviewed by <strong>the</strong> <strong>City</strong> each <strong>of</strong> <strong>the</strong> shop drawings will be identified as having<br />
received such review, being so stamped and dated. Shop drawings stamped<br />
"REJECTED" will be returned to <strong>the</strong> Design-Build Firm <strong>for</strong> correction and re-submittal<br />
with <strong>the</strong> required correction indicated on <strong>the</strong> shop drawing or listed on a "Shop Drawing<br />
Review sheet”.<br />
If submitted drawings or schedules show a departure or variation from <strong>the</strong> Contract<br />
Requirements which are in <strong>the</strong> interest <strong>of</strong> <strong>the</strong> <strong>City</strong> and to be so minor as not to involve a<br />
change in Contract Price or time <strong>for</strong> per<strong>for</strong>mance, <strong>the</strong> <strong>City</strong> may return <strong>the</strong> reviewed<br />
drawings without noting an exception.<br />
If <strong>the</strong> Design-Build Firm makes a determination that conflicts with any part <strong>of</strong> <strong>the</strong> Design<br />
Criteria Package, <strong>the</strong> Design-Build Firm shall give written notice <strong>the</strong>re<strong>of</strong> to <strong>the</strong> Project<br />
Manager. This does not constitute a change order until accepted by <strong>the</strong> <strong>City</strong>.<br />
Re-submittals will be handled in <strong>the</strong> same manner as first submittals. On re-submittals,<br />
<strong>the</strong> Design-Build Firm shall direct specific attention on <strong>the</strong> transmittal and on re-<br />
32<br />
Design-Build Services <strong>for</strong> Seawall Stabilization and Repair Project RFP 11-12-033