06.12.2012 Views

Liebert Mini-Mate2, 8 Ton - Emerson Network Power

Liebert Mini-Mate2, 8 Ton - Emerson Network Power

Liebert Mini-Mate2, 8 Ton - Emerson Network Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

2.4.3 Piping Connections and Coolant Requirements<br />

11<br />

Site Preparation and Installation<br />

Drain Line<br />

! CAUTION<br />

The drain line must not be trapped outside the unit, or water may back-up in drain pan.<br />

Drain is internally trapped.<br />

This line may contain boiling water. Use copper or other suitable material for the drain line.<br />

Sagging condensate drain lines may inadvertently create an external trap.<br />

A 3/4 in. (19.1 mm) female pipe thread (FPT) connection is provided for the evaporator coil condensate<br />

drain. This line also drains the humidifier, if applicable. The drain line must be located so it will not<br />

be exposed to freezing temperatures. The drain should be the full size of the drain connection.<br />

The evaporator drain pan includes a float switch to prevent unit operation if drain becomes blocked.<br />

Figure 6 Drain installation<br />

Correct<br />

Unit<br />

Continuous slope<br />

away from unit<br />

These are external traps also, although<br />

unintentional. Lines must be rigid<br />

enough to not bow between supports.<br />

Humidifier drain water can approach<br />

100° Celsius.<br />

Incorrect<br />

Unit<br />

Unit<br />

Do not externally<br />

trap the unit<br />

Incorrect

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!