Exhibit B-4<br />

Project Ownership, Partners &<br />

Experience<br />

Project Timeline<br />

ADDITIONAL SUPPORT | SECTION 19<br />

Project 43_ND1 - St. Joseph River Hydropower<br />

18<br />

Project Information<br />

Project Contact<br />

Tim Sexton, University of Notre Dame<br />

Project Title: St. Joseph River Hydropower Project in Downtown South Bend<br />

Project Description<br />

Project Location<br />

Project Category<br />

Industry Alignment<br />

Project Partners<br />

Project Experience<br />

The University will construct a 1.83 megawatt facility on the city-owned dam downtown south bend in 2016, completed in 2019. Power fr<br />

the facility would be conveyed to campus by way of an underground transmission line, a distance of about 1.5 miles. However, it would<br />

reduce campus carbon emissions, increase electric reliability, fix a portion of campus utility costs, provide academic research opportunit<br />

and create strong partnerships with local governments.<br />

South Bend, IN, St. Joseph County<br />

Infrastructure<br />

Energy<br />

University of Notre Dame<br />

City of South Bend<br />

Pending<br />

Project Start Date<br />

1/1/2016<br />

Project End Date 12/31/2019<br />

Start within 12 months? Yes<br />

Project Timeline 2016 Construction, full completion in 2019<br />

EXECUTIVE SUMMARY THE REGION ENGAGED CURRENT TRENDS<br />

STATE OF THE REGION<br />

& QUALITY OF PLACE<br />

Project Budget & Funding<br />

Year 1 capital expenditures<br />

($) $5,000,000.00<br />

Year 2 capital expenditures<br />

($) $5,000,000.00<br />

Year 3 capital expenditures<br />

($) $5,000,000.00<br />

Year 4 capital expenditures<br />

($) $5,000,000.00<br />

Year 5 capital expenditures<br />

($) $0.00<br />

Total Capital Expenditures $20,000,000.00<br />

Ongoing expenditures for<br />

operations, maintenance,<br />

etc. ($) $0.00<br />

Total project budget $20,000,000.00<br />

Description of Capital<br />

Expenditures<br />

Construction costs<br />

Description of Ongoing<br />

Expenditures<br />

N/A<br />

Total project budget $20,000,000.00<br />

Local public funding $0.00<br />

Private funding $20,000,000.00<br />

Non-profit funding $0.00<br />

Other funding $0.00<br />

RCI funding required? No<br />

RCI funding needed $0.00<br />

RCI funding proportion of<br />

cap ex 0%<br />

Total funding $20,000,000.00<br />

Variance between budget &<br />

funding $0.00<br />

Private/public/other funding<br />

ratio 100 / 0 / 0<br />

43_ND1_St. Joseph River Hydropower<br />

REGIONALCITIESOFNORTHERN<strong>INDIANA</strong>.ORG |<br />

325<br />

VISION & STRATEGY PROJECTS<br />

STAKEHOLDERS, EXECUTION<br />

& STRUCTURAL CHANGES<br />

BENCHMARKING<br />

& MEASUREMENT<br />

ADDITIONAL SUPPORT

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!