challenges that need to be illuminated and processed.<br />
The prerequisite for a constructive dialogue<br />
with the authorities involved is a thorough<br />
analysis, which is conducted in on-going contact<br />
with the external advisors of the Company and<br />
in an agreed procedure with the local government<br />
in question.<br />
The Company has a number of properties under<br />
development at all times. It is not always predictable,<br />
how quickly the development process<br />
can take place, since the politicians will often<br />
have to be heard in the process, and sometimes<br />
our wishes for rapid development conflict with<br />
local government interests in ot<strong>her</strong> development<br />
projects and plans.<br />
It is under constant evaluation to what level the<br />
development process is to be taken before we<br />
look for potential developers, since their considerations<br />
may be of importance to the most<br />
appropriate final framing of the Company’s<br />
wishes in connection with the district plan. In<br />
some situations, it will be profitable to offer a<br />
building right for sale at an early stage and to<br />
develop the possibilities in cooperation with a<br />
developer. In ot<strong>her</strong> situations, the best overall<br />
result is achieved by not putting the property up<br />
for sale until a district plan has been agreed, or<br />
at least until a public enquiry has been opened<br />
for the proposed district plan. Furt<strong>her</strong>more,<br />
some district plans may be of a somewhat controversial<br />
nature, and in those cases it may be<br />
of relevance to the district plan process that it<br />
is backed by a developer, so that the politicians<br />
who agree to the district plan may know that<br />
the project in question will be carried out if the<br />
district plan is accepted.<br />
Several significant development projects of the<br />
Company concern properties in Copenhagen<br />
City, and we were pleased to find that the district<br />
plans for both Margretheholm and for the<br />
property in Hambrosgade were finalised.<br />
Margretheholm has t<strong>her</strong>efore now been finally<br />
transferred to the Sjælsø Gruppen, w<strong>her</strong>eas<br />
the building right to the beautiful and well laidout<br />
office building of 23,000 sq m, which the<br />
Dutch architect Erick van Egeraat has designed<br />
for the site in Hambrosgade, is still up for sale.<br />
At the end of <strong>2007</strong>, a developer paid an option<br />
premium in order to gain time to look into the<br />
possibilities of financing the purchase and the<br />
subsequent construction work. But the option<br />
owner in question had to give up in his attempt<br />
to provide financing in the somewhat turbulent<br />
financial market in early 2008.<br />
At Strandpromenaden 33-39 close to Svanemøllen<br />
in Copenhagen, the Company has taken over<br />
four neighbouring villas on four sites with a total<br />
area of just below 9,000 sq m. Toget<strong>her</strong> with<br />
the Cornerstone Group, which would be interested<br />
in buying the building right and construct<br />
new buildings, we have made an agreement<br />
about jointly investigating the possibilities of<br />
developing a project that is so convincing that<br />
the local government will allow us to demolish<br />
the four villas and build the area with primarily<br />
new homes. We have t<strong>her</strong>efore decided to invite<br />
six architectural firms to participate in a competition<br />
for ideas, a so-called parallel commission,<br />
to shed light on the possibilities for a unique<br />
new project that will fit into the special character<br />
of the local area and may contribute positively<br />
to life in the area.<br />
The property at Følager 5 in Valby, Copenhagen,<br />
is one of several properties in the area near the<br />
new station, w<strong>her</strong>e the local government has<br />
invited the neighbouring landowners to partici-<br />
pate in a process aimed towards an overall development<br />
plan for the entire area. We believe<br />
that t<strong>her</strong>e is basis for building around 20,000<br />
sq m of primarily service providers on our site.<br />
Still, a clarification of this point would require a<br />
new district plan, which cannot be made until<br />
the overall plan has been negotiated. T<strong>her</strong>efore,<br />
a new district plan will not be ready until some<br />
time in 2009.<br />
Two previous development projects, the Ny<br />
Tøjhus first at Amager and next at Holmen, have<br />
required considerable resources on the part of<br />
Freja, even long after the district plans were<br />
agreed and the building rights sold. With regard<br />
to Holmen, the City Surveyor had his so far most<br />
extensive and most complicated registration<br />
procedure that came to an end in <strong>2007</strong> after<br />
almost ten years. At the Ny Tøjhus the development<br />
process proposed by Freja has had to be<br />
divided into a number of smaller stages in order<br />
to provide as little hindrance as possible to<br />
the successive developers. The last office building<br />
is now so far progressed in the construction<br />
process that the development can now be<br />
terminated. What remains is the process of creating<br />
the opening of the district plan towards<br />
Njalsgade. This process awaits the approval by<br />
the local government of the project proposed by<br />
the buyer for a building intended to form the<br />
eastern neighbour of, and to be separated by a<br />
coming square from, the three warehouses that<br />
used to belong to the FDB (the Federation of<br />
Danish Cooperative Societies).<br />
A district plan already exists for the property at<br />
Frederiksborgvej 71 in Allerød, north of Copenhagen.<br />
However, we do not consider the project<br />
made possible in the district plan completely upto-date,<br />
and t<strong>her</strong>efore we have cooperated with<br />
62 63<br />
the architectural firm of Vandkunsten and SLA<br />
(landscape architects and urban development<br />
planners) for the design of an alternative building<br />
proposal, which has also been discussed with<br />
the local authorities. Whet<strong>her</strong> we will attempt<br />
to have the district plan changed depends on<br />
whet<strong>her</strong> we can find developers who would prefer<br />
the new building plan. In the current market<br />
for new homes, it is not quite easy to make the<br />
building of new homes in Allerød profitable.<br />
The property at Rolighedsvej 1 in Ballerup west<br />
of Copenhagen is situated close to the city centre<br />
and the station. This site could become an<br />
important asset in the local government’s wishes<br />
to develop the somewhat uninspiring environment<br />
in the city centre. The local government<br />
has initiated a development process w<strong>her</strong>e they<br />
seek contributions to Vision 2020 in dialogue<br />
with the citizens. Upon agreement with the local<br />
administration, Freja has offered our views<br />
of the process based on our own site, just as<br />
we have commented on both deficiencies and<br />
opportunities in general for the city centre and<br />
submitted a sketch drawn up in cooperation<br />
with the architect Erik Nobel for a comprehensive<br />
project covering our site and the two adjacent<br />
sites to the north and south, respectively.<br />
At Herstedlund in Albertslund west of Copenhagen,<br />
all building rights have been sold long ago,<br />
and many of the new homes are being built.<br />
As part of the project, we have taken on the<br />
construction of a tenants’ house, which is to<br />
be transferred to the homeowners’ association.<br />
This project was supposed to have started in<br />
<strong>2007</strong>, but was not initiated until January 2008.<br />
The delay was caused by the incomprehensible<br />
result of the tender process. This meant that the<br />
architects of Dorte Mandrup Arkitekter had to