EUROCODE 2 WORKED EXAMPLES - Federbeton
EUROCODE 2 WORKED EXAMPLES - Federbeton
EUROCODE 2 WORKED EXAMPLES - Federbeton
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
EC2 – worked examples 4-5<br />
Considering that the TT element is cast under procedures subjected to a highly efficient<br />
quality control, in which the concrete cover length is also assessed, the value of Δcdev can<br />
be taken as 5 mm.<br />
We obtain from relation (3.1):<br />
c = c + Δc = 25 + 5 = 30 mm .<br />
nom min dev<br />
Calculating now the concrete cover for longitudinal bars.<br />
We have:<br />
c = 12 mm .<br />
min,b<br />
We obtain from table 4.4N - EC2:<br />
c = 25 mm .<br />
min,dur<br />
Moreover:<br />
Δc dur, γ = 0 ;<br />
Δc dur,st = 0 ;<br />
Δc = 0 .<br />
dur,add<br />
From relation (3.2):<br />
cmin = max (c min,b ; cmin,dur +Δcdur, γ −Δcdur,st −Δc<br />
dur,add;<br />
10 mm) =<br />
= max (12; 25 + 0 – 0 – 0; 10 mm) = 25 mm .<br />
We obtain from relation (3.1):<br />
c = c + Δc = 25 + 5 = 30 mm .<br />
nom min dev<br />
Note that for the ordinary reinforcement bars, the concrete cover for stirrups is “dominant”.<br />
In this case, the concrete cover for longitudinal bars is increased to: 30 + 8 = 38 mm .<br />
Table of Content<br />
Fig. 4.3<br />
Calculating now the concrete cover for strands.