SieMpelkaMp | MACHInERy AnD PLAntS<br />
Design phase<br />
During the eleven-month developmenttime,<br />
the project participants of both companies<br />
worked closely together. <strong>Siempelkamp</strong><br />
contributed the know-how from a<br />
number of similar projects and EUROPIPE<br />
contributed with its experience from<br />
operating pipeline manufacturing lines.<br />
Because of the large technical experience<br />
of the <strong>Siempelkamp</strong> engineers, EUROPIPE<br />
gave them a lot of freedom during the<br />
design process. During routine meetings,<br />
mainly the integration of the new press in<br />
the available space and the transport of<br />
components with weights up to 216 t (238<br />
US tons) all the way into the production<br />
hall were discussed.<br />
the blueprints of the old foundation could<br />
be provided by EUROPIPE so that structural<br />
engineers only had to check whether the<br />
existing foundation would be suitable for<br />
the new press.<br />
Einsetzen des Presstisches<br />
the new press, just as the old one, is<br />
expected to operate for many decades.<br />
<strong>Siempelkamp</strong> used the finite element<br />
method to prove the fatigue strength of<br />
the main components including the frame,<br />
the moving beam, and the foundation<br />
stands.<br />
Both parties will confirm that the partnership<br />
at eye level was the base for the<br />
project’s success. this success would not<br />
have been possible without the high qualification<br />
and the experiences in dealing<br />
with extraordinary large presses on both<br />
sides as well as realistic demands.<br />
Exactly on schedule<br />
After the castings, made in <strong>Siempelkamp</strong>’s<br />
own foundry, were completed and the<br />
press was assembled by <strong>Siempelkamp</strong> in<br />
Krefeld, the functional test and performance<br />
tests were carried out. they progressed<br />
successfully so that EUROPIPE was<br />
Press at <strong>Siempelkamp</strong> ready for acceptance<br />
test by customer<br />
Bent plate for acceptance at <strong>Siempelkamp</strong><br />
66<br />
67<br />
able to commence with the disassembly of<br />
the old press as scheduled. the disassembly<br />
of the old machine took almost two<br />
weeks. In only five weeks, <strong>Siempelkamp</strong><br />
assembled and started up the new press.<br />
the edges of the first plate were bent on<br />
August 18, 2008 – on the scheduled date.<br />
Already the first plate was according to<br />
specifications and was made into a saleable<br />
pipe. Since August 2008 the press produced<br />
continuously in two-shift operation.<br />
<strong>Siempelkamp</strong> specialists monitored the<br />
start-up on site for three months. One employee<br />
stayed until January 2009, but did<br />
not have to get involved anymore at the<br />
end of his time.<br />
the first plates were bent by manual<br />
operation. Already after three days the<br />
press was operating in automatic mode<br />
for individual plates, after a week for<br />
several plates in series. Regular material<br />
flow was achieved after two to three