City Development Plan for Allahabad Final Report<br />
7.2.2<br />
Treatment &<br />
Distribution<br />
Facilities<br />
7.2.3<br />
Coverage &<br />
numbers of municipal tube wells, 216 numbers of mini municipal tube wells,<br />
and 2448 numbers of municipal hand pumps are satisfying 137 MLD water<br />
demand of the city. The private hand pumps and tube wells are satisfying the<br />
54 MLD water demand of the city, which is not in the records of JS and JN.<br />
Table 20 details out the water works for Allahabad municipal area.<br />
It has also been estimated that the intake of water from Yamuna River in 2003<br />
was 80 MLD whereas the remaining 137 MLD water drawn from 157 deep<br />
tube wells operated by the JS (Table 21). The quality of water is reported to be<br />
of acceptable standard.<br />
Table 21: Total Water Production in 2003<br />
Sl. No. Source of Supply Capacity (MLD)<br />
1 Surface water (Yamuna river) 80<br />
2 Tube wells 137<br />
Total Production 217<br />
Source: JICA 11 & JS Reports 12 .<br />
The raw water from River Yamuna is being tapped (80 MLD) at Karelibagh<br />
raw water pumping station which is pumped to Khusro Bagh water works for<br />
treatment before it is supplied to the consumers.<br />
The existing condition of the treatment plant is poor. The clarriflocculation<br />
unit of the plant, which is one of the main units of the WTP, is not functional.<br />
The sedimentation tank is serving the purpose of the clarriflocculation unit.<br />
Coagulant is being added in raw water in the raw water channel for the<br />
coagulation and sedimentation of suspended solids in the sedimentation tanks.<br />
Total capacity of settling tank is 177 MLD. Effluent from the sedimentation<br />
tank passes from the filter beds of rapid gravity sand filters. Total filtration<br />
capacity of the filter is about 135 MLD. The filtered water is chlorinated by<br />
chlorine gas with the help of chlorine toners. The water after filtration and<br />
chlorination is stored in the clear water storage tanks. Water from the clear<br />
water storage tanks is pumped and served to the community and about 35% of<br />
total water being supplied to the city is being fulfilled by this WTP.<br />
Table 22: Water Situation Analysis in 2003<br />
Sl. No. Description Detail<br />
1 Total Population in 2003 1049800 nos<br />
2 Total Municipal water production 80+137=217 mld<br />
3 15% losses 180 lpcd<br />
Net water supply 180 lpcd (say)<br />
Source: Allahabad Master Plan 2021<br />
Based on JN estimates, private supplies account for an additional 20%. The<br />
present per capita supply of water is approximately 210 lpcd<br />
Allahabad city has been divided into 12 water supply zones. Out of these 12<br />
zones (Table 23, Figure 25), three zones are being served by surface water<br />
43