12. Time Schedule Table and Milestones<br />
The <strong>NeuLAND</strong> production scheme comprises the full installation of one double-plane<br />
per month. <strong>NeuLAND</strong> will be built from 30 planes, therefore, the full detector will be<br />
ready three years after the beginning of production. This time scheme takes into account<br />
three months for the startup of production lines for the supplying companies and three<br />
months for the full system integration after building of the last double-plane. Another<br />
three months will be needed for the invitation for tender and the order placing after the<br />
financing commitments.<br />
With the expected financing commitments in Q3/2012 we can define the following milestones,<br />
which are visualized in figure 12.1:<br />
1. 20%-detector readiness Q1/2014<br />
2. first physics experiment with 20% detector in Q3/2014 in Cave C at GSI<br />
3. <strong>NeuLAND</strong> readiness Q4/2015<br />
4. first physics experiment with complete <strong>NeuLAND</strong> in Q3/Q4/2016 in Cave C at<br />
GSI<br />
Nr. Task Name<br />
1 <strong>NeuLAND</strong> Construction Phase<br />
2 invitation to tender / order placing<br />
3 startup production lines at companies<br />
4 production of <strong>NeuLAND</strong> submodules<br />
5 20% detector produced<br />
6 20% detector system integration<br />
7 Milestone 1: 20% detector readiness<br />
8 20% detector first experiment in Cave C<br />
9 Milestone 2: first experiment using 20% detector performed<br />
10 full detector produced<br />
11 full detector system integration<br />
12 Milestone 3: full detector readiness<br />
13 full <strong>NeuLAND</strong> calibration and first physics experiment<br />
14 Milestone 4: completion of first physics experiment with full <strong>NeuLAND</strong><br />
2012 2013 2014 2015 2016 2017<br />
. Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt<br />
Figure 12.1.: Graphical display of the time schedule of <strong>NeuLAND</strong> production including<br />
dependencies and milestones.<br />
31.12.<br />
01.10.<br />
01.10.<br />
31.12.<br />
93