12. Time Schedule Table and Milestones<br />

The <strong>NeuLAND</strong> production scheme comprises the full installation of one double-plane<br />

per month. <strong>NeuLAND</strong> will be built from 30 planes, therefore, the full detector will be<br />

ready three years after the beginning of production. This time scheme takes into account<br />

three months for the startup of production lines for the supplying companies and three<br />

months for the full system integration after building of the last double-plane. Another<br />

three months will be needed for the invitation for tender and the order placing after the<br />

financing commitments.<br />

With the expected financing commitments in Q3/2012 we can define the following milestones,<br />

which are visualized in figure 12.1:<br />

1. 20%-detector readiness Q1/2014<br />

2. first physics experiment with 20% detector in Q3/2014 in Cave C at GSI<br />

3. <strong>NeuLAND</strong> readiness Q4/2015<br />

4. first physics experiment with complete <strong>NeuLAND</strong> in Q3/Q4/2016 in Cave C at<br />

GSI<br />

Nr. Task Name<br />

1 <strong>NeuLAND</strong> Construction Phase<br />

2 invitation to tender / order placing<br />

3 startup production lines at companies<br />

4 production of <strong>NeuLAND</strong> submodules<br />

5 20% detector produced<br />

6 20% detector system integration<br />

7 Milestone 1: 20% detector readiness<br />

8 20% detector first experiment in Cave C<br />

9 Milestone 2: first experiment using 20% detector performed<br />

10 full detector produced<br />

11 full detector system integration<br />

12 Milestone 3: full detector readiness<br />

13 full <strong>NeuLAND</strong> calibration and first physics experiment<br />

14 Milestone 4: completion of first physics experiment with full <strong>NeuLAND</strong><br />

2012 2013 2014 2015 2016 2017<br />

. Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt . Qt<br />

Figure 12.1.: Graphical display of the time schedule of <strong>NeuLAND</strong> production including<br />

dependencies and milestones.<br />

31.12.<br />

01.10.<br />

01.10.<br />

31.12.<br />