13. Organization and Distribution of<br />
Responsibilities<br />
The detector design was developed from a subgroup of the R 3 B collaboration, called<br />
the <strong>NeuLAND</strong> Working Group. The members, as of today, are listed in appendix A.<br />
The <strong>NeuLAND</strong> Working Group, convened currently by Konstanze Boretzky, GSI, and<br />
her deputy, Ushasi Datta Pramanik, SINP, will build the <strong>NeuLAND</strong> detector. A close<br />
contact to the R 3 B Technical Coordinator and the Project Coordinator enables a smooth<br />
embedding of the <strong>NeuLAND</strong> detector into the R 3 B’s full setup.<br />
The responsibilities for the different subtasks are closely related to their associated funding<br />
profile, as laid out in chapter 11. In table 13, we summarize the required tasks for<br />
the construction phase of <strong>NeuLAND</strong> and assign the institutes with key responsibilities.<br />
More details on the tasks are found in the numerated list below.<br />
Item <strong>NeuLAND</strong> Task Short Description Responsible Institutes<br />
1 Submodules purchase, assembly, test SINP, TU Darmstadt,<br />
& double planes PNPI, TU Dresden,<br />
HZDR, U Cologne,<br />
U Frankfurt, GSI<br />
2 Sample Tests using electron beams HZDR<br />
3 Mechanics detector & double-plane frames GSI<br />
full integration<br />
4 Electronics quality control, integration GSI<br />
5 HV System production, quality control, integration PNPI, GSI<br />
Table 13.1.: Layout of the subtasks for the building phase of <strong>NeuLAND</strong> and the responsibity<br />
distribution. The item numbers refer to the list in the text, accordingly.<br />
1. <strong>NeuLAND</strong> Submodules and Double-Planes<br />
This task comprises first, the purchase of scintillator bars, photomultipliers and<br />
needed peripherals like voltage supplies and read-out channels, second, the assembly<br />
of <strong>NeuLAND</strong> submodules and its acceptance tests, third, the arrangement of<br />
<strong>NeuLAND</strong> submodules into double-planes. The work load is shared amongst the<br />
partners according to the financial contributions. Since, for practical reasons, the<br />
<strong>NeuLAND</strong> submodules will be built on-site at GSI/<strong>FAIR</strong>, the external partners<br />
will send personnel to GSI/<strong>FAIR</strong> for the assembly and testing procedure.<br />