13. Organization and Distribution of<br />

Responsibilities<br />

The detector design was developed from a subgroup of the R 3 B collaboration, called<br />

the <strong>NeuLAND</strong> Working Group. The members, as of today, are listed in appendix A.<br />

The <strong>NeuLAND</strong> Working Group, convened currently by Konstanze Boretzky, GSI, and<br />

her deputy, Ushasi Datta Pramanik, SINP, will build the <strong>NeuLAND</strong> detector. A close<br />

contact to the R 3 B Technical Coordinator and the Project Coordinator enables a smooth<br />

embedding of the <strong>NeuLAND</strong> detector into the R 3 B’s full setup.<br />

The responsibilities for the different subtasks are closely related to their associated funding<br />

profile, as laid out in chapter 11. In table 13, we summarize the required tasks for<br />

the construction phase of <strong>NeuLAND</strong> and assign the institutes with key responsibilities.<br />

More details on the tasks are found in the numerated list below.<br />

Item <strong>NeuLAND</strong> Task Short Description Responsible Institutes<br />

1 Submodules purchase, assembly, test SINP, TU Darmstadt,<br />

& double planes PNPI, TU Dresden,<br />

HZDR, U Cologne,<br />

U Frankfurt, GSI<br />

2 Sample Tests using electron beams HZDR<br />

3 Mechanics detector & double-plane frames GSI<br />

full integration<br />

4 Electronics quality control, integration GSI<br />

5 HV System production, quality control, integration PNPI, GSI<br />

Table 13.1.: Layout of the subtasks for the building phase of <strong>NeuLAND</strong> and the responsibity<br />

distribution. The item numbers refer to the list in the text, accordingly.<br />

1. <strong>NeuLAND</strong> Submodules and Double-Planes<br />

This task comprises first, the purchase of scintillator bars, photomultipliers and<br />

needed peripherals like voltage supplies and read-out channels, second, the assembly<br />

of <strong>NeuLAND</strong> submodules and its acceptance tests, third, the arrangement of<br />

<strong>NeuLAND</strong> submodules into double-planes. The work load is shared amongst the<br />

partners according to the financial contributions. Since, for practical reasons, the<br />

<strong>NeuLAND</strong> submodules will be built on-site at GSI/<strong>FAIR</strong>, the external partners<br />

will send personnel to GSI/<strong>FAIR</strong> for the assembly and testing procedure.<br />