CONCENTRATING SOLAR SYSTEMS UNIT<br />
3.3.3 PS10<br />
10 MW <strong>Solar</strong> Thermal Power Plant for Southern Spain<br />
Participants: SOLUCAR (E) Coordinator, CIEMAT (E), DLR (D), Fichtner (D).<br />
Contacts:<br />
Funding:<br />
Duration:<br />
Valerio Fernán<strong>de</strong>z (valerio.fernan<strong>de</strong>z@pssm.abengoa.com); Félix<br />
M. Téllez (felix.tellez@ciemat.es)<br />
The Project has received a 5-M€ subsidy from the European<br />
Commission DG TREN ENERGIE Program.(Ref. NNE5-1999-<br />
00356), and 1.2 M€ from the Andalusian Government.<br />
July 2001 to July 2004 (participation of CIEMAT exten<strong>de</strong>d by specific<br />
Agreement up to plant startup in March 2007).<br />
Background: The PS10 Project, begun in 1999, has had a long history to date<br />
and awakens many expectations in the solar community, as it is the first<br />
commercial solar tower initiative insi<strong>de</strong> and outsi<strong>de</strong> of Spain. For the PSA, the<br />
PS10 project is of enormous importance as the obligatory reference that focuses<br />
research and technology <strong>de</strong>velopment and channels feedback from industry,<br />
in this case the SOLUCAR company, and a public research organism<br />
like the CIEMAT, for <strong>de</strong>finition of joint <strong>de</strong>velopment strategies for heliostats,<br />
advanced concentrators, solar receivers, software co<strong>de</strong>s and tools and thermal<br />
storage, all subjects which have generated projects fun<strong>de</strong>d by the Ministry<br />
of Education and Science PROFIT Program.<br />
Purposes: The main purpose of the PS10 Project (Planta <strong>Solar</strong> 10) is to <strong>de</strong>sign,<br />
build and operate a commercial solar thermal power plant with tower<br />
and heliostat field system having a rated gross power of 11 MW. This plant<br />
has been installed in the municipal limits of Sanlúcar la Mayor in the Province<br />
of Seville and is expected to be inaugurated in March 2007.<br />
Achievements in <strong>2006</strong>: In <strong>2006</strong>, construction and installation were completed<br />
and commissioning was begun. During this stage, the PSA-CIEMAT advised<br />
Solucar on operating procedures and selection of instrumentation for special<br />
variables, such as solar flux infrared measurement during receiver adjustment<br />
and testing, etc.<br />
Publications: [3.19]<br />
Figure 3.11 Infrared measurement of the PS10 receiver during commissioning (14/12/06) from<br />
three field observation points<br />
3.3.4 HICONPV<br />
High Concentration PV Power System.<br />
Participants: Solúcar Energía (coordinator), DLR, Fraunhofer ISE, CIEMAT-<br />
PSA, CIEMAT, RWE (D), Ben Gurion Univ. (IL), EDF and Univ. Malta.<br />
Contact: Jesús Fernán<strong>de</strong>z Reche (Jesús.fernan<strong>de</strong>z@psa.es)<br />