PLATAFORMA SOLAR DE ALMERÍA<br />

Figure 3.17 Ormat turbine at the 60-m level in the CESA-1 tower<br />

It was originally planned to prepare the Ormat turbine for operation with<br />

biofuel in <strong>2006</strong>. As the machine had not been operated for two years, before<br />

starting it up again, it was run with kerosene to make sure the turbine was in<br />

good condition before modifying it. However, the task was har<strong>de</strong>r than originally<br />

thought. Some auxiliary components were ad<strong>de</strong>d as a new monitoring<br />

system first, and then continued with a general subsystem control, e.g., for<br />

the turbine oil and gear systems, tower communications system – control<br />

room, main electric box, fuel lines, fuel metering valve, and water-cooling<br />

system with its associated pumps and piping. Finally, it was attempted to<br />

start up the turbine. Since the cause of failures could not be <strong>de</strong>termined with<br />

the means available at the <strong>Plataforma</strong> <strong>Solar</strong>, specialists from Ormat came at<br />

the beginning of November. But in spite of about three dozen attempts, they<br />

were unable to start up the turbine either. The most likely reason for the<br />

problem was that <strong>de</strong>posits may have formed in the metering valve capillary<br />

tubes (Figure 3.18). The valve was sent back to the manufacturer in the U.S.<br />

where it was thoroughly cleaned out, some pieces were replaced for its future<br />

use with biofuel and it was recalibrated.<br />

In 2007, the Ormat turbine will be restarted, 100% biofuel components will<br />

be modified and 100% renewable solar tests performed, and finally the Turbec<br />

turbine and the new multilayer tube receiver will be installed at the 45-m<br />

level.<br />

Figure 3.18 The Metering Valve (fuel lines disconnected)<br />