Environmental procedure EP 5.1<br />

responsible for the project. At <strong>Bengalla</strong>, prior consultation with the<br />

Environmental Section is required before disturbance;<br />

• a visual inspection will be conducted for Aboriginal artifacts. Any<br />

artifacts found will be managed in accordance with the relevant<br />

procedures;<br />

• a visual flora and fauna inspection will be conducted to monitor for<br />

threatened species and to identify fauna that might require relocation<br />

prior to clearing. Environmental Services will be notified of any issues<br />

arising from the inspection;<br />

• a visual assessment of the vegetation will be conducted to identify<br />

available seed and timber resources to be collected or removed;<br />

• an assessment will be made of the depth, volume and characteristics of<br />

the topsoil to be removed;<br />

• diversion banks and drains will be constructed to prevent soil erosion as<br />

required by CNA’s erosion and sediment control management plan;<br />

• contractors undertaking vegetation removal, topsoil stripping and<br />

overburden removal will be briefed on their environmental<br />

responsibilities.<br />

4.2 Vegetation Removal<br />

Vegetation, not required for other purposes, and rocks will be pushed into<br />

windrows located away from any standing trees.<br />

All grass will be left to be recovered with the topsoil.<br />

Trees and logs will be cut to a size manageable by the shovel. Following<br />

topsoil removal and blasting, this material will be pushed on to the pre-strip<br />

area for removal with the overburden.<br />

A watch will be maintained for Aboriginal objects during the clearing and<br />

soil removal operations. If any objects are encountered, clearing will cease<br />

in that area and the Manager Environmental Services will be notified.<br />

4.3 Soil Stripping<br />

Soil stripping will be to be undertaken in accordance with the <strong>Mining</strong><br />

Operations Plan.<br />

Topsoil will be stripped by bulldozer or scraper to the depth determined by<br />

the MOP or until subsoil is observed by the plant operator or supervisor.<br />

Guidance on stripping depth will be sought from the Specialist,<br />

Rehabilitation and Landcare if there is any uncertainty.<br />

Topsoil stripping will not be undertaken in windy conditions that will cause<br />

excessive dust to be generated (see EP 8.2 Dust Management, Mobile<br />

Equipment).<br />

The water content of the soil to be stripped is an important consideration:<br />

title<br />

EP 5.1<br />

REHABILITATION<br />

date issued<br />

3/8/04<br />

revision status<br />

1.3<br />

date reviewed<br />

20/1/05<br />

Printed documents are uncontrolled. Check the <strong>Coal</strong> & Allied Intranet for the latest version of this document.<br />

page<br />

2 of 8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!