Rehabilitation & Landscape<br />

Management Plan<br />

Table 1<br />

Rehabilitation & Landscape Management Plan Requirements<br />

Condition Requirement Section<br />

33<br />

By end of July 2007, the Applicant must prepare (and following approval<br />

implement) a detailed Rehabilitation and Landscape Management Plan<br />

for the development, in consultation with affected agencies, and to the<br />

satisfaction of the DPI and the Director-General. This plan must be<br />

prepared by suitably qualified expert/s whose appointment/s have been<br />

approved by the Director-General, and must include a:<br />

(a)<br />

Rehabilitation Management Plan;<br />

This<br />

RLMP<br />

(b)<br />

(c)<br />

Final Void Management Plan; and<br />

Mine Closure Plan.<br />

34<br />

The Rehabilitation Management Plan must include:<br />

(a) the rehabilitation objectives for the site; 3.1<br />

(b)<br />

(c)<br />

(d)<br />

(e)<br />

a description of the short, medium, and long term measures that<br />

would be implemented to:<br />

• rehabilitate the site; and<br />

• manage the remnant vegetation and habitat on the site;<br />

detailed assessment and completion criteria for the rehabilitation<br />

of the site;<br />

a detailed description of how the performance of the rehabilitation<br />

of the mine would be monitored over time to achieve the stated<br />

objectives;<br />

a detailed description of what measures would be implemented<br />

over the next 5 years to rehabilitate and manage the landscape of<br />

the site including the procedures to be implemented for:<br />

3.2 &<br />

3.3<br />

3.4<br />

3.2.5 &<br />

4.0<br />

3.2<br />

• progressively rehabilitating areas disturbed by mining; 3.2.3 &<br />

3.2.4<br />

• implementing revegetation and regeneration; 3.2.4<br />

• protecting areas outside the disturbance areas; 3.2.1<br />

• managing impacts on fauna; 3.2.1<br />

• conserving and reusing topsoil; 3.2.1 &<br />

3.2.3<br />

• collecting and propagating seed for rehabilitation works; 3.2.1<br />

• salvaging and reusing material from the site for habitat<br />

enhancement;<br />

3.2.1<br />

• controlling weeds and feral pests; 3.2.6<br />

• controlling access; 3.2.5<br />

• bushfire management; 3.2.6<br />

• managing any identified conflicts between the rehabilitation of<br />

the mine and Aboriginal cultural heritage; and<br />

3.2.1<br />

Ref: 071025 bmc rehabilitation & landscape mp Page 2