Environmental procedure EP 5.1<br />

• reducing the flow rate of water across the ground, particularly on<br />

exposed surfaces and in areas where water congregates;<br />

• constructing catch drains, contour ploughing and the placement of hay<br />

bales;<br />

• regrading gullies to a stable land form;<br />

• the placement of coarse material; and<br />

• revegetation.<br />

Rehabilitated areas, prestripping areas and other areas that are prone to<br />

erosion will be inspected regularly. Any erosion identified will be treated<br />

promptly to minimise damage to the land and protect the quality of water on<br />

the site (see EP7.1 Water Management).<br />

4.16 Dust Control<br />

If it becomes necessary to use the water cart or water sprays to control dust<br />

prior to topsoil stripping, on topsoil stockpiles or rehabilitated areas, clean<br />

water (ie: non-saline water) must be used. The use of saline water may<br />

degrade soil quality and kill vegetation (see EP8.2 Dust Management,<br />

Mobile Equipment).<br />

4.17 Monitoring and Reporting<br />

A qualified surveyor will survey all rehabilitated areas. This information<br />

will be used to compile the annual rehabilitation report to the DMR and<br />

CNA’s internal reporting requirements.<br />

An annual rehabilitation audit is undertaken to ensure all relevant<br />

management plans and <strong>Rio</strong> <strong>Tinto</strong> Standards are achieved.<br />

Annual inspections of rehabilitated areas will be carried out in conjunction<br />

with the DMR and DLWC to determine progress against government<br />

completion criteria. The Environmental Specialist Rehabilitation &<br />

Landcare will address any actions coming out of these inspections.<br />

5. Responsibilities<br />

Environmental<br />

Specialist<br />

Rehabilitation &<br />

Landcare<br />

• Overview CNA’s timber clearing, topsoil stripping<br />

and rehabilitation program.<br />

• Provide advice where required on topsoil stripping,<br />

topsoil management and rehabilitation<br />

• Conduct annual management audits of topsoil<br />

stockpiles and rehabilitated areas<br />

• Maintain a topsoil stockpile register<br />

• Preparation of DMR annual rehabilitation reports<br />

and CNA rehabilitation reports<br />

• Facilitate annual DMR / DLWC inspections and<br />

address any resultant actions<br />

title<br />

EP 5.1<br />

REHABILITATION<br />

date issued<br />

3/8/04<br />

revision status<br />

1.3<br />

date reviewed<br />

20/1/05<br />

Printed documents are uncontrolled. Check the <strong>Coal</strong> & Allied Intranet for the latest version of this document.<br />

page<br />

7 of 8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!