Corporation shall at the same time inform the Contractor whether it claims compensation for delay and<br />

recover the same as a penalty for delay. No price escalation will be allowed in the event of extension of<br />

time granted on genuine grounds.<br />

CLAUSE - V I:<br />

FINAL CERTIFICATE :<br />

On completion of the work, the Contractor shall be furnished with a certificate by the Corporation of such<br />

completion, but not such certificate be given not shall the work considered to be completed until the<br />

Contractor shall have removed from the area of the premises (to be distinctly marked by the Corporation<br />

in the site plan) on which the work shall be executed, all scaffolding, surplus materials and rubbish, and<br />

cleaned off the dirt from all woodwork, doors, windows, walls, floors or other parts of any structure, in<br />

upon or about which the work is to be executed or of which he may have had possession for the purpose<br />

of the execution thereof nor until the work shall have been measured by the authorised officer of Orissa<br />

Industrial Infrastructure Development Corporation in accordance with the rules of the department whose<br />

measurements shall be binding and conclusive against the Contractor. If the Contractors shall fail to<br />

comply with the requirements of this clause as to removal of scaffolding, surplus materials and rubbish,<br />

and cleaning off dirt on or before the date fixed for the completion of the work, the authorised officer of<br />

the Corporation may at the expense of the Contractor remove such scaffoldings, surplus materials and<br />

rubbish, and dispose of the same as he thinks fit and clean off such dirt as aforesaid, and the Contractor<br />

shall forthwith pay the amount of all expenses incurred and shall have no claim in respect and such<br />

scaffolding or surplus materials as aforesaid except for any sum actually realised by the sale thereof.<br />

CLAUSE - VII :<br />

PAYMENT ON INTERMEDIATE CERTIFICATE TO BE REGARDED AS ADVANCE AND BILL<br />

TO BE SUBMITTED MONTHLY :<br />

A bill shall be submitted by the Contractor each month or before the date fixed by the Corporation for all<br />

works executed in the previous month and the authorised officer of the Corporation or his subordinate<br />

shall take the requisite measurement for the purpose of having the same verified and the claim as far as<br />

admissible, adjusted if possible, before the expiry of ten days from the presentation of the bill. If the<br />

Contractor does not submit the bill within the time fixed as aforesaid, the authorised officer of the<br />

Corporation or his subordinate shall measure up the said work in the presence of the Contractor whose<br />

counter signature to the measurement list shall be sufficient warrant and the authorised officer of the<br />

Corporation or his subordinate shall prepare a bill from such list which shall be binding on the Contractor<br />

in all respects.<br />

Provided that, if any balance of the 7% (seven percent) security is outstanding from each such payment<br />

shall be deducted so much, not exceeding 5% as may be necessary to make up the balance of the<br />

security. All such intermediate payments to the Contractor shall be regarded as payments by way of<br />

advance against the final payment only and not as payments for work actually done and completed and<br />