The Contractor shall submit a copy of the test results to the authorised Officer of the Corporation<br />
immediately after the test. In case the Contractor fails to carry out the tests in the manner prescribed<br />
in the relevant I.S. Code, the same shall be carried out by the Corporation and the cost so involved<br />
shall be recovered from any amount due to the Contractor.<br />
36. In case some machineries are available with the Corporation the same can be utilised by<br />
the Contractor on payment of the prescribed hire charges to Corporation. The hire charges as fixed<br />
by the Corporation shall be binding on the Contractor.<br />
37. The Contractor has to provide a net work of pipe lines for proper watering and curing of<br />
the works and provide outlet points at suitable places at his own cost. Curing shall be done by the<br />
Contractor at his own cost with an arrangement of flexible pipes and nozzles etc. The cost of energy<br />
charges, for running of pumps, machineries and lighting arrangements etc. are to be borne by the<br />
Contractor. If at any stage , it is observed that the curing being done by the Contractor is not proper<br />
and acceptable to the Corporation then the same shall be got done by the Corporation<br />
departmentally, or through other agency on actual cost + 25% basis without an prior notice to the<br />
Contractor. This amount with 25% surcharge shall be recovered by the Corporation from any<br />
amount due to the Contractor.<br />
38. The Corporation will at his discretion and convenience and for the duration of the<br />
execution of the work may provide land for construction of Contractors field, office, godowns work<br />
shops and assembly yard required for the execution of the contract nearest to the site. The<br />
tenderer shall at his own cost construct all these temporary buildings structures and provide suitable<br />
water supply and sanitary arrangement as approved by the authorised officer of <strong>IDCO</strong> and other<br />
inspectorates.<br />
39. MATERIALS OBTAINED FROM DISMANTLING:<br />
If the Contractor in the course of execution of the work is called upon to dismantle any<br />
part for reasons other than those stipulated specifically in the tender else where the materials<br />
obtaining in the work of dismantling etc. will be considered as the Corporation’s property and will be<br />
disposed off to the best advantage of the Corporation.<br />
40. WORKS ON SUNDAYS & HOLIDAYS:<br />
For carrying out works on Sundays and holidays except curing, the Contractor will<br />
approach the authorised Officer of <strong>IDCO</strong> or his representative at least two days in advance and<br />
obtain permission in writing. The Contractor shall observe all labour laws and other statutory rules<br />
and regulations in force. In case of any violation of such laws, rules and regulations, consequence if<br />
any, including the cost there to shall be exclusively borne by the Contractor and the Corporation<br />
shall have no liability whatsoever on this account.<br />
58