SPECIAL CONDITION<br />

1. Notwithstanding any other condition in DTCN, No water will normally be supplied by Corporation.<br />

The Contractor is to arrange water for the work at his own cost. The Contractor will lay the pipe line net<br />

work required for the construction purpose at his own cost. No delay in construction is permissible on<br />

the ground of paucity of water. If the water is availed from the Corporation source by the Contractor,<br />

water charges will be levied as per prevailing rate and the amount will be recovered from the his bill.<br />

Service roads are to be constructed by Contractor at his own cost.<br />

2. No time extension will be granted on the ground of scarcity of water, communication, material<br />

and machinery etc.<br />

3. The responsibility to locate Govt. approved quarry and burrow area lies with the Contractor.<br />

4. Wherever levels are to be taken it will be the responsibility of Contractor to get the same done<br />

through concerned Junior Engineer and checked by the Assistant Engineer.<br />

5. The Contractor will submit a detailed programme of completion of work with methodology for<br />

execution of each item of work at the time of execution of agreement.<br />

6. All machineries will be arranged by the Contractor at his own cost in proper time.<br />

7. The Contractor shall abide by the relevant Act like Minimum wages, Employees Provident Fund,<br />

ESI etc. and Rules and Regulations in force of the state of Orissa from time to time for the labour<br />

employed in construction work. The contractor shall be fully and solely responsible for any<br />

compensation/ fine that may be imposed for violation of the said Rules/Regulations/Act.<br />

8. For any bad quality of work the amount of award given by any consumer court/ judicial court will<br />

be recovered from the executing Contractor.<br />

9. Where the agreement rates are more than 25% of the estimated rate, no extra quantity beyond<br />

the agreement quantity should be executed without the prior written approval of competent authority of<br />

<strong>IDCO</strong>.<br />

10. Additional performance security shall be deposited by the successful bidder when the bid<br />

amount is seriously unbalanced i.e. less than the estimated cost by more than 10%. In such an event<br />

the successful bidder will deposit the additional performance security to the amount of the differential<br />

cost of the bid amount and 90% of the estimated cost in shape of Bank draft or Bank Guarantee of any<br />

nationalized Bank.<br />

11. For any additional quantities up to 25% on any item, the Contractor will be paid at the approved<br />

tender rate.<br />

8