<strong>Nepal</strong> <strong>Telecom</strong><br />

<strong>Nepal</strong> Doorsanchar Company Limited<br />

Clause<br />

No.<br />

Particulars of <strong>Nepal</strong> <strong>Telecom</strong>’s Requirements<br />

requirements b) for detection of errors and c) any other tests as found<br />

necessary by the vendor.<br />

6.1.2 During the provisional testing, besides the above tests, the following<br />

conditions shall also be fulfilled:<br />

Bidder shall state as :<br />

Fully Compliant / Partially<br />

Compliant/Non Compliant<br />

1. All hardware specified in the contract shall be fully functional.<br />

2. Errorless functioning of each software module of the system.<br />

3. User interfaces and report layouts as expected<br />

4. Totality of entries, queries, reports, check points and controls for<br />

efficient operation of the module<br />

5. The following documents shall be provided to <strong>Nepal</strong> <strong>Telecom</strong>:<br />

a) Installation Manual<br />

b) Interconnection details including scripts if used.<br />

c) Functional description of the entire system<br />

d) Data dictionary, table structure and their relationship<br />

e) System operational and maintenance manuals<br />

f) Users guides for all types of users in the system<br />

6. All documents shall be in paper and electronic media.<br />

7. After completion of the Provisional Acceptance Testing, <strong>Nepal</strong><br />

<strong>Telecom</strong> will issue the Provisional Acceptance Certificate<br />

(PAC)or Rejection Letter within fourteen (14) days from the date<br />

of completion of the provisional acceptance testing. If all the tests<br />

are successfully performed or if only some minor deficiencies are<br />

noticed, the Provisional Acceptance Certificate will be issued<br />

with the condition that the minor deficiencies will be cleared<br />

within one month from the date of issuance of the certificate.<br />

8. Issuance of Provisional Acceptance Certificate will not prejudice<br />

any claim with respect to any defect or malfunction, which may<br />

subsequently develop during the warranty period.<br />

9. <strong>Nepal</strong> <strong>Telecom</strong> will put the system for commercial operation after<br />

the Provisional Acceptance Testing is completed provided the<br />

acceptance testing is completed successfully according to the<br />

contract schedule. If the testing and commissioning of the system<br />

is delayed beyond the contract schedule period and/or if there are<br />

major deficiencies, <strong>Nepal</strong> <strong>Telecom</strong> will have full authority to put<br />

the system into commercial service before issuing Provisional<br />

Acceptance Certificate. Under such circumstances, the supplier is<br />

required to make the basic functions and services in place, ready<br />

for bringing the system into production use and provide<br />

maintenance service (technical support and maintenance of<br />

Hardware and Software) from the date the system is brought into<br />

commercial service at no additional cost to <strong>Nepal</strong> <strong>Telecom</strong>.<br />

Tender No. NDCL/19/066-67 for Supply, Delivery, Installation & Commissioning of the Over The Air (OTA)<br />

Platform System<br />

Page 37 of 54