Particulars of <strong>Nepal</strong> <strong>Telecom</strong>’s Requirements<br />
requirements b) for detection of errors and c) any other tests as found<br />
necessary by the vendor.<br />
6.1.2 During the provisional testing, besides the above tests, the following<br />
conditions shall also be fulfilled:<br />
Bidder shall state as :<br />
Fully Compliant / Partially<br />
Compliant/Non Compliant<br />
1. All hardware specified in the contract shall be fully functional.<br />
2. Errorless functioning of each software module of the system.<br />
3. User interfaces and report layouts as expected<br />
4. Totality of entries, queries, reports, check points and controls for<br />
efficient operation of the module<br />
5. The following documents shall be provided to <strong>Nepal</strong> <strong>Telecom</strong>:<br />
a) Installation Manual<br />
b) Interconnection details including scripts if used.<br />
c) Functional description of the entire system<br />
d) Data dictionary, table structure and their relationship<br />
e) System operational and maintenance manuals<br />
f) Users guides for all types of users in the system<br />
6. All documents shall be in paper and electronic media.<br />
7. After completion of the Provisional Acceptance Testing, <strong>Nepal</strong><br />
<strong>Telecom</strong> will issue the Provisional Acceptance Certificate<br />
(PAC)or Rejection Letter within fourteen (14) days from the date<br />
of completion of the provisional acceptance testing. If all the tests<br />
are successfully performed or if only some minor deficiencies are<br />
noticed, the Provisional Acceptance Certificate will be issued<br />
with the condition that the minor deficiencies will be cleared<br />
within one month from the date of issuance of the certificate.<br />
8. Issuance of Provisional Acceptance Certificate will not prejudice<br />
any claim with respect to any defect or malfunction, which may<br />
subsequently develop during the warranty period.<br />
9. <strong>Nepal</strong> <strong>Telecom</strong> will put the system for commercial operation after<br />
the Provisional Acceptance Testing is completed provided the<br />
acceptance testing is completed successfully according to the<br />
contract schedule. If the testing and commissioning of the system<br />
is delayed beyond the contract schedule period and/or if there are<br />
major deficiencies, <strong>Nepal</strong> <strong>Telecom</strong> will have full authority to put<br />
the system into commercial service before issuing Provisional<br />
Acceptance Certificate. Under such circumstances, the supplier is<br />
required to make the basic functions and services in place, ready<br />
for bringing the system into production use and provide<br />
maintenance service (technical support and maintenance of<br />
Hardware and Software) from the date the system is brought into<br />
commercial service at no additional cost to <strong>Nepal</strong> <strong>Telecom</strong>.<br />