Clause<br />
No.<br />
Particulars of <strong>Nepal</strong> <strong>Telecom</strong>’s Requirements<br />
5) Installation and Commissioning testing<br />
6) System database and its management<br />
7) System Optimization and Performance measurement<br />
8) System Fault Diagnostics<br />
Training shall be conducted in such a way that trainees, after<br />
completion of the training, shall be able to handle, operate and<br />
maintain the OTAP system independently & effectively.<br />
Bidder shall state as :<br />
Fully Compliant / Partially<br />
Compliant/Non Compliant<br />
The trained personnel shall later be deputed for installation, testing,<br />
operation, maintenance and repair of the system in <strong>Nepal</strong>.<br />
11.2 Training Cost<br />
11.2.1 The bidder shall quote the price for the training. The price quoted shall<br />
include tuition fee, training materials, accommodation and local<br />
transport for the trainees. Two way air-fare and daily allowances for<br />
trainees shall be borne by <strong>Nepal</strong> <strong>Telecom</strong>.<br />
11.2.2 The trainees shall be insured for medical treatment and all kinds of<br />
risks during their stay in the supplier’s country. The insurance costs<br />
shall be included in the training cost.<br />
11.2.3 Detailed breakdown of training cost showing cost of each of the<br />
components indicated above shall be provided. The training cost shall<br />
be considered for evaluation of the bid.<br />
12 Factory Inspection and Testing of the Equipment<br />
12.1 All the equipments / applications shall be tested in the factory before<br />
the shipment. The test results shall be supplied with the equipment.<br />
<strong>Nepal</strong> <strong>Telecom</strong> shall depute two (2) Senior Inspectors to participate in<br />
the factory inspection and acceptance test of the offered system for a<br />
period of five (5) working days at the manufacturer’s premises. The<br />
supplier shall notify <strong>Nepal</strong> <strong>Telecom</strong>, the starting date of the inspection<br />
by <strong>Nepal</strong> <strong>Telecom</strong>’s Inspectors at least thirty days prior to the<br />
shipment. The bidder shall provide all the necessary test equipment,<br />
tools and help to test the system performance. The supplier shall<br />
correct, before the shipment of the equipment, all the deficiencies<br />
found during the testing.<br />
12.2 The bidder shall quote the price for the factory test separately. The<br />
price shall include accommodation, local transportation and medical<br />
insurance coverage for <strong>Nepal</strong> <strong>Telecom</strong>’s Senior Inspectors during the<br />
factory acceptance test. Two way air-fare and daily allowances for the<br />
Inspectors will be borne by <strong>Nepal</strong> <strong>Telecom</strong>.<br />
The cost of the factory inspection and testing will be considered<br />
for evaluation.<br />
13 Support Requirement<br />
1. 24 x 7 support from <strong>Nepal</strong> office & escalation to head quarters /<br />
2nd & 3rd tier support as required - list down locations of head<br />
quarters / 2nd & 3rd tier support<br />
2. 1 hours (Service Level Agreement) SLA response time for severe<br />
technical issues<br />
Tender No. NDCL/19/066-67 for Supply, Delivery, Installation & Commissioning of the Over The Air (OTA)<br />
Platform System<br />
Page 42 of 54