at worst, a legal challenge to the selection decision from an aggrieved supplier. The<br />
Purchasing Office must be present at any debriefing sessions.<br />
10.3 Mandatory standstill period<br />
As soon as a decision has been made to award a contract or conclude a framework<br />
agreement, the contracting authority must inform all bidders (preferably by fax or email).<br />
They should be provided with details <strong>of</strong> the award criteria; their own score and that <strong>of</strong> the<br />
winner (where practicable); the name <strong>of</strong> the successful tenderer; the reasons for the decision<br />
including the characteristics and relative advantages <strong>of</strong> the successful tender and reasons (if<br />
any) why they did not meet the technical specification. The award notice must contain a<br />
statement <strong>of</strong> either when the standstill period is expected to end or the date before which the<br />
contracting authority will not enter into a contact. The contracting authority must then wait<br />
10 days before actually entering into the contract or concluding the framework agreement.<br />
10.4 Reporting Requirements<br />
Contracting authorities are required to report, for each public supply and services contract,<br />
details <strong>of</strong> the value, procedure, type <strong>of</strong> goods and the nationality <strong>of</strong> the successful tenderer to<br />
H.M. Treasury. Purchasing Office will collect this information annually and issue a report<br />
on behalf <strong>of</strong> the <strong>University</strong>.<br />
11 DISPUTES AND REMEDIES<br />
Failure to adhere to the Regulations may cause a legal challenge by an aggrieved supplier, or<br />
investigation by the European Commission. This can result in a contract being suspended or<br />
even completely set aside and/or compensation being paid to tenderers. Purchasing Office<br />
must be contacted immediately if there is any indication that a tenderer is unhappy with<br />
the conduct <strong>of</strong> a tender or the final result, even if the complaint appears petty or without<br />
foundation, so that action can be taken to avoid escalation.<br />
Purchasing Procedures December 2011