Preparation Phase<br />

Jacking Steelwork & Over plating<br />

Before any work could be started a substantial amount of<br />

preparation was required.<br />

Large areas of the collector mains required over plating to<br />

ensure there was enough “mechanical strength” to carry out<br />

the replacement task.<br />

Additional steelwork was erected to provide “jacking points”<br />

for splitting the flanges with hydraulic jacks.<br />

Pressure control and purging operations<br />

Nitrogen purge points and re-circulating gas stabbings were “hottapped”<br />

into the crossover mains to facilitate pressure control and<br />

purging operations.<br />