Introduction<br />

Due to the poor condition of the pipe work and the losses of<br />

containment, we were faced with three options.<br />

1. Repair the current pipe work by “over plating”.<br />

2. Remove the <strong>Coke</strong> side Gas Collecting <strong>Main</strong> and<br />

“<strong>Crossover</strong> mains” altogether and operate the plant on a<br />

single Gas Collecting <strong>Main</strong>.<br />

3. Remove the <strong>Crossover</strong> mains and replace with new.<br />

4