<strong>Crossover</strong> <strong>Main</strong> <strong>Replacement</strong><br />

Removal of “Bend Section”<br />

The bend section of the crossover was disconnected form the<br />

horizontal section to prevent slewing as the horizontal section<br />

was lifted out.<br />

An 80 tonne crane set-up on the Ram track side of the<br />

Battery was used to execute the lift.<br />

After disconnection of the flanges and breaking up of the<br />

heavy tar deposit at the flange, the bend was lowered to the<br />

floor.<br />