<strong>Crossover</strong> <strong>Main</strong> <strong>Replacement</strong><br />
Removal of “Bend Section”<br />
The bend section of the crossover was disconnected form the<br />
horizontal section to prevent slewing as the horizontal section<br />
was lifted out.<br />
An 80 tonne crane set-up on the Ram track side of the<br />
Battery was used to execute the lift.<br />
After disconnection of the flanges and breaking up of the<br />
heavy tar deposit at the flange, the bend was lowered to the<br />
floor.<br />