Preparation Phase<br />
Welding inspection & Pressure testing<br />
All the new pipe work, including the service pipe work was<br />
manufactured and tested at Fairwood Fabrications Ltd<br />
workshop.<br />
Before leaving the workshop every weld was 100% MPI<br />
tested and each pipe section pressure tested with<br />
compressed air to one and a half times the maximum working<br />
pressure.<br />
A quality assurance (QA) file complied throughout the<br />
manufacturing process was produced and formed part of the<br />
Health and Safety file.<br />