Process Highlights & Friction Points<br />
• MoI identifies and develops requirements<br />
• Equipment is procured by DOL<br />
• MMC tracks equipment and requirements<br />
• NLC receives /ships equipment to RLC<br />
• Items are not in inventory<br />
• Delayed entry into country<br />
• Equipment shipped to RLC for distribution<br />
• RLC distributes to MSPs<br />
• Establishment of distribution plan<br />
• Establishing New Equipment Training (NET)<br />
• Limited MSP available<br />
ANP Equipment Fielding<br />
2-3<br />
Weeks<br />
MoI<br />
DOL<br />
MMC<br />
NLC<br />
RLC<br />
MSP<br />
Process Improvements:<br />
MoI<br />
• Requirements generation<br />
• Strategic planning<br />
• Bureaucratic issue process<br />
• Multiple Tashkils<br />
• Accountability<br />
• Established ASL determined and procured<br />
prior to fielding<br />
• Efficient Push and Movement of Equipment to<br />
Unit<br />
RLC<br />
• Accountability<br />
• New equipment training<br />
• Cross leveling<br />
• ASL establishment packages<br />
• HQs/Units receive equipment<br />
• Conduct New Equipment Training<br />
• NET planned but not conducted by all<br />
2-3<br />
Weeks<br />
NET<br />
2-3<br />
Days<br />
New<br />
Equipment<br />
Training<br />
HQs<br />
HQs/ Units<br />
• Sustainment package with initial<br />
fielding<br />
• New Equipment Training (NET) plan and<br />
Execution<br />
Critical Node (Down)<br />
Units<br />
Friction Points<br />
Flow of Equipment<br />
BLUF:<br />
• Equipment procured without full sustainment consideration. Results in part shortages and subsequently vehicles awaiting repairs.<br />
• Push letters not issued in a timely manner delaying fielding often > 30 days.<br />
• Once Title Transfers are complete vehicle visibility is lost and may be given to different recipients.<br />