Wharton Component<br />

Cost Apportionment for the Recommended Plan<br />

Feature Federal Non-Federal Total<br />

Lands and Damages $4,116,000 $4,116,000<br />

Relocations $785,000 $785,000<br />

Fish and Wildlife Mitigation $765,000 $765,000<br />

Channels and Canals $1,354,000 $1,354,000<br />

Levees and Floodwalls $15,430,000 $15,430,000<br />

Preconstruction, Engineering, Design $1,093,000 $57,000 $1,150,000<br />

Construction Management $929,000 $929,000<br />

Santa Fe Ditch (by City, Sec 104) $2,900,000 $2,900,000<br />

Subtotal $19,571,000 $7,858,000 $27,429,000<br />

5% Cash by Non-Fed Sponsor ($1,371,000) $1,371,000<br />

Additional cash for 35% minimum ($371,000) $371,000<br />

Total Cost Apportionment $17,829,000 $9,600,000 $27,429,000<br />

Cost Share Percentages 65.00% 35.00%<br />

October 26, 2006<br />