Lower Colorado River Basin - Onion Creek<br />

Flood Damage Reduction and Ecosystem Restoration Project<br />

Land Acquisition Costs<br />

Concern:<br />

Land acquisition costs for the for ecosystem restoration components nts exceeds<br />

25 percent <strong>of</strong> project cost. Land acquisition costs constitute 888<br />

8 percent <strong>of</strong> the<br />

ecosystem cost <strong>of</strong> the Williamson Creek component, 51 percent for the Onion<br />

Creek Forest/Yarrabee Bend Segment component, and 31 percent for the Timber<br />

Creek component.<br />

Reason: Paragraph 7.m <strong>of</strong> EP 1165-2-502 502 states, “As a general rule, land value should not<br />

exceed 25 percent <strong>of</strong> total project costs {for Ecosystem projects]. Projects that<br />

exceed 25% would not likely to be given a high budget priority.”<br />

Resolution: Williamson Creek was removed from the recommended plan. p<br />

Yarrabee and<br />

Timber Creek were reviewed to determine if lesser land could be acquired. The land<br />

acquisition percentage for Yarrabee was reduced to 49% but Timber r Creek remained<br />

the same. However, this land acquisition cost is relatively minor in relation to the<br />

associated flood damage reduction project.<br />

Resolution Impact: Resolved<br />

9/8/2006<br />

84