14.03.2015 Views

GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

the planning process are provided each year from the NOAA Program Planning and Integration Office in<br />

its Planning Guidance Memorandum to the programs.<br />

5.1.2 Programming<br />

The Programming phase of the PPBES process provides the fiscal and programmatic linkage between<br />

NOAA’s strategic plan and its budget. The Office of Strategic Planning (OSP) is responsible for the<br />

programming phase of the PPBES process. It aids the <strong>GOES</strong>-R program office in translating the high<br />

level outcomes contained in the NOAA Strategic Plan into clear and understandable program objectives.<br />

OSP provides guidance for each year’s programming phase in its yearly Programming Phase Overview.<br />

The Program Office uses this guidance as it builds its budget for the upcoming cycle.<br />

5.1.3 Budgeting<br />

Budget submissions will occur at least annually to support the <strong>GOES</strong>-R Program budget formulation and<br />

spend plans process.<br />

The <strong>GOES</strong>-R Program Office will issue annual budget and program guidance (the Annual <strong>GOES</strong>-R<br />

Budget Call) to the Flight and Ground Segment Projects in November of each year to update the projects<br />

on the current program of record, to identify any changes in program configuration, to solicit an update to<br />

the currently approved funding baseline, and to prescribe the appropriate reporting format. The Flight<br />

and Ground Segment Projects will respond with their preliminary submissions in January of the following<br />

year and final submissions in March.<br />

The <strong>GOES</strong>-R Program Office/Program Control and the projects will engage in annual budget discussions<br />

in order to support NOAA budget preparation prior to the annual Commerce budgeting process. The<br />

Annual Budget and Program Guidance Letter to the Projects will provide the necessary guidance and<br />

information to the Project for the development of their budget responses. This guidance and information<br />

will consist of:<br />

• Approved Instruments<br />

• Description of the scope of the work being performed by the Project<br />

• Programmatic direction regarding ongoing and future contracts and the exercising of options<br />

• Schedule constraints and launch readiness dates (LRDs)<br />

• Identifies Fiscal Years being considered in the Department of Commerce’s submission to the<br />

Office of Management and Budget (OMB) and Congress<br />

• Funding constraints and yearly phasing – by fiscal year<br />

• Adjustments to prior years funding<br />

• General instructions for providing a response<br />

The Annual Budget and Program Guidance letter will request a quotation from the Flight and Ground<br />

Segment Projects in the format as directed by the <strong>GOES</strong>-R annual budget and program guidance. The<br />

Projects will develop their responses based upon the instructions and guidance provided and knowledge<br />

of their contract funding / costing needs, manpower support requirements, and institutional support. The<br />

Projects will make every attempt to stay within the funding guidelines. If an over-guidance response is<br />

necessary, the Project(s) will document the rationale and provide the documentation within their response<br />

to the Program. The Projects will provide an initial submission to the Program in the January timeframe.<br />

With the initial submission, the Projects and the Program will engage in discussions so that the Projects’<br />

response is fully understood and any changes, if required, can be developed prior to the final submission.<br />

The Flight project will ensure that the GSFC Center Director has reviewed the NASA budget submission<br />

prior to its final submission to the Program in the March timeframe of each year. The Program Control<br />

and the Project Managers will ensure that open dialogue as the <strong>GOES</strong>-R team assembles, submits and<br />

Page 37 of 75

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!