APB for major program reported in Selected Acquisition Report (SAR)<br />

SAR annually and quarterly<br />

Unit Cost Report<br />

Cost breaches triggered by 15% growth in current or 30% growth in original Program Acquisition Unit<br />

(PAUC) or Average Procurement Unit Cost (APUC)<br />

NOAA Reporting<br />

In addition to the monthly PMRs, status reports and presentations, the <strong>GOES</strong>-R GPO is required to<br />

submit quarterly EVM Reports and annual Operational Analyses Reports to NOAA. The project<br />

performance reports are to include an integrated performance curve graph that depicts the following<br />

cumulative variances:<br />

• BCWS or Planned Value (PV)<br />

• ACWP or Actual Cost (AC)<br />

• BCWP or Earned Value (EV)<br />

Project performance reports will also include the following cumulative EVMS data:<br />

• Budget at Completion (BAC)<br />

• CV<br />

• CPI<br />

• Estimate at Completion, adjusted for the current CPI; (EAC1)<br />

• Variance at Completion, adjusted for the current CPI; (VAC1)<br />

• Estimate to Complete, adjusted for the current CPI; (ETC1)<br />

• SV<br />

• SPI<br />

• Cost/Schedule Index (CSI)<br />

• Estimate at Completion, adjusted for both CPI & SPI (EAC2)<br />

• Variance at Completion, adjusted for both CPI & SPI<br />

• Estimate to Complete, adjusted for both CPI & SPI<br />

• Expected Completion Date, based on the current SPI<br />

• Level of Effort<br />

• Cost Performance Index Chart<br />

• Cost/Schedule Variance Trends Chart<br />

• Estimate at Completion (EAC) Chart<br />

• Use of Management Reserve (MR) PMB Plot<br />

• Use of MR Cost variance Chart<br />

• MR EAC Chart<br />

• Over Target Baseline PMB EAC Chart<br />

• Effect of Over Target Baseline on CV Chart<br />

• Six Period Summary<br />

• Executive Summary<br />

Along with the quantitative data listed above, the project performance report shall include a discussion of<br />

any cost or schedule variances exceeding 10% (a CPI, SPI or CSI less than 0.90 or greater than 1.10).<br />

This discussion will explain the cause(s) of the variance and whether or not the project still expects to<br />

achieve its performance goals. The report will also discuss the corrective actions that will be taken to<br />