14.03.2015 Views

GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

A CPI or SPI of 1.00 indicates 100% performance for budget and schedule. CPI/SPI greater than 1.00<br />

indicates performance that is ahead of schedule or below cost where as a CPI/SPI less than 1.00 indicates<br />

performance behind schedule or above cost.<br />

Index Green Yellow Red<br />

CPI CPI>0.95 0.95> CPI > 0.90 CPI< 0.90<br />

SPI SPI>0.95 0.95> SPI > 0.90 SPI< 0.90<br />

Figure 14: EVM Indices Thresholds<br />

Any index change resulting in a “red” assessment must be reported to the Program Office immediately,<br />

whereas an index change resulting in a “yellow” assessment will be reported at the next month’s review.<br />

This applies to both the current month and the cumulative indices. EVM indices will be reported at the<br />

monthly status review to the GSFC Center Management Council (CMC) and NOAA Program<br />

Management Council (PMC). The program office shall work with the Projects to determine corrective<br />

action required. Any major component index which falls into the red zone requires immediate<br />

notification of the Program Office. The color coded index system will only be reported internally to the<br />

program where as any variances outside of the 10 % threshold will be reported externally to NESDIS,<br />

NOAA, and the Department level as required.<br />

Integrated Baseline Review (IBR)<br />

An IBR is a joint assessment conducted by the Government Program Manager (PM) and the contractor(s)<br />

to verify the realism and accuracy of the Performance Measurement Baseline (PMB). This involves<br />

verifying the technical content of the baseline and assessing the realism and accuracy of the related<br />

resources (performance budget and Integrated Master Schedule (IMS)). The IBR is unlike the Validation<br />

Review (VR) that focuses on EVMS compliance with ANSI/EIA-748A. Instead the IBR focuses on<br />

assessing the realism of the baseline.<br />

The contractor(s) and Government shall support the formal IBR as early as practicable and should be<br />

initiated no later than 180 calendar days after contract award/Authority to Proceed (ATP), the exercise of<br />

significant contract options and the incorporation of major modifications or as otherwise agreed upon. In<br />

addition, the Government will request to conduct a Pre-IBR sixty days prior to the formal IBR date.<br />

The IBR should not be considered as a one-time event or single point review. IBRs are also performed at<br />

the discretion of the PM or when major events occur within the life of a program. These events may be a<br />

significant shift in content and/or time-phasing of the PMB or a major milestone. An IBR should also be<br />

conducted whenever an Over Target Baseline (OTB) or Over Target Schedule (OTS) is implemented.<br />

The IBR should prepare risk evaluation criteria in technical, schedule, cost, resource and management<br />

processes. Technical risk is the ability of the project’s technical plan to achieve the objectives of the<br />

scope of work. Schedule risk is the adequacy of the time allocated for performing the defined tasks to<br />

successfully achieve the project schedule objectives. Cost risk is the ability of the PMB to successfully<br />

execute the project and attain cost objectives, recognizing the relationships between budget, resources,<br />

funding, schedule, and scope of work. Resource risk is the timely availability of personnel, facilities, and<br />

equipment to perform the defined tasks needed to execute the program successfully. Management<br />

processes risk is the degree to which the management processes provide effective and integrated<br />

technical/schedule/cost planning and baseline change control.<br />

The Government and contractor(s) will begin discussing the coverage of the IBR as soon as possible after<br />

contract award. The IBR focuses on assessing the baseline realism at the lowest level and other baseline<br />

related risk evaluations as necessary. Sixty days prior to the IBR (in conjunction with the Pre-IBR), the<br />

contractor(s) shall be required to provide all supporting and preparatory documentation to the<br />

Page 41 of 75

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!