GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
A CPI or SPI of 1.00 indicates 100% performance for budget and schedule. CPI/SPI greater than 1.00<br />
indicates performance that is ahead of schedule or below cost where as a CPI/SPI less than 1.00 indicates<br />
performance behind schedule or above cost.<br />
Index Green Yellow Red<br />
CPI CPI>0.95 0.95> CPI > 0.90 CPI< 0.90<br />
SPI SPI>0.95 0.95> SPI > 0.90 SPI< 0.90<br />
Figure 14: EVM Indices Thresholds<br />
Any index change resulting in a “red” assessment must be reported to the Program Office immediately,<br />
whereas an index change resulting in a “yellow” assessment will be reported at the next month’s review.<br />
This applies to both the current month and the cumulative indices. EVM indices will be reported at the<br />
monthly status review to the GSFC Center Management Council (CMC) and NOAA Program<br />
Management Council (PMC). The program office shall work with the Projects to determine corrective<br />
action required. Any major component index which falls into the red zone requires immediate<br />
notification of the Program Office. The color coded index system will only be reported internally to the<br />
program where as any variances outside of the 10 % threshold will be reported externally to NESDIS,<br />
NOAA, and the Department level as required.<br />
Integrated Baseline Review (IBR)<br />
An IBR is a joint assessment conducted by the Government Program Manager (PM) and the contractor(s)<br />
to verify the realism and accuracy of the Performance Measurement Baseline (PMB). This involves<br />
verifying the technical content of the baseline and assessing the realism and accuracy of the related<br />
resources (performance budget and Integrated Master Schedule (IMS)). The IBR is unlike the Validation<br />
Review (VR) that focuses on EVMS compliance with ANSI/EIA-748A. Instead the IBR focuses on<br />
assessing the realism of the baseline.<br />
The contractor(s) and Government shall support the formal IBR as early as practicable and should be<br />
initiated no later than 180 calendar days after contract award/Authority to Proceed (ATP), the exercise of<br />
significant contract options and the incorporation of major modifications or as otherwise agreed upon. In<br />
addition, the Government will request to conduct a Pre-IBR sixty days prior to the formal IBR date.<br />
The IBR should not be considered as a one-time event or single point review. IBRs are also performed at<br />
the discretion of the PM or when major events occur within the life of a program. These events may be a<br />
significant shift in content and/or time-phasing of the PMB or a major milestone. An IBR should also be<br />
conducted whenever an Over Target Baseline (OTB) or Over Target Schedule (OTS) is implemented.<br />
The IBR should prepare risk evaluation criteria in technical, schedule, cost, resource and management<br />
processes. Technical risk is the ability of the project’s technical plan to achieve the objectives of the<br />
scope of work. Schedule risk is the adequacy of the time allocated for performing the defined tasks to<br />
successfully achieve the project schedule objectives. Cost risk is the ability of the PMB to successfully<br />
execute the project and attain cost objectives, recognizing the relationships between budget, resources,<br />
funding, schedule, and scope of work. Resource risk is the timely availability of personnel, facilities, and<br />
equipment to perform the defined tasks needed to execute the program successfully. Management<br />
processes risk is the degree to which the management processes provide effective and integrated<br />
technical/schedule/cost planning and baseline change control.<br />
The Government and contractor(s) will begin discussing the coverage of the IBR as soon as possible after<br />
contract award. The IBR focuses on assessing the baseline realism at the lowest level and other baseline<br />
related risk evaluations as necessary. Sixty days prior to the IBR (in conjunction with the Pre-IBR), the<br />
contractor(s) shall be required to provide all supporting and preparatory documentation to the<br />
Page 41 of 75