GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Identify Proposed<br />
Change<br />
(Start)<br />
Perform<br />
Analysis<br />
(technical)<br />
Needs further<br />
analysis<br />
Needs further<br />
analysis<br />
Contracts<br />
Negotiates<br />
(if applicable)<br />
No<br />
Draft<br />
CCR<br />
Form<br />
CM Reviews<br />
Assigns CCR#<br />
Engineering<br />
Review<br />
Board<br />
Valid?<br />
Yes<br />
Perform<br />
Analysis<br />
(cost, schedule, risk)<br />
Configuration<br />
Control Board<br />
Approved?<br />
Yes<br />
Effect<br />
Level I?<br />
Yes<br />
No<br />
No<br />
NESDIS<br />
RPSI<br />
CM Archives<br />
Request<br />
CM Archives<br />
Request<br />
Figure 18: Program Level Change Request Process (Level II)<br />
The change process is composed of three main components; the Engineering Review Board (ERB), the<br />
Configuration Control Board (CCB), and the Program Configuration Control Board (PCCB).<br />
Engineering Review Board (ERB): The Engineering Review Board determines the validity and necessity<br />
of proposed requirements changes and other contract applicable document (SOW, CDRL, and WBS)<br />
prior to their introduction into the formal CM process. The ERB will by chaired by the Systems<br />
Engineering Lead at the program or project level. At the project level, the ERB chairman may designate<br />
an alternate at his/her discretion. At the program level, either the Ground Segment Project Systems<br />
Engineering Lead or the Flight Project Systems Engineering Lead may be called upon as the acting ERB<br />
chairman in the absence of the Program Systems Engineering Lead. The chairman is responsible for<br />
inviting members of the engineering review board in accordance with the subject matter of the change.<br />
These members will finalize a technical impact analysis of the proposed change. The CCR may also be<br />
submitted to the Program/Project Control team for an initial cost and/or schedule impact analysis. If the<br />
change is validated, the ERB will provide its recommendation and impact study results to the<br />
Configuration Control Board (CCB).<br />
Configuration Control Board (CCB): The Configuration Control Board will review and consider the<br />
CCR and all analysis associated with it. CCB members will make a recommendation to the SPD or<br />
Project Managers, who are responsible for final disposition. If a CCR is approved, Contracts staff will be<br />
notified for their review for contractual implications.<br />
The Program CCB (PCCB): The PCCB is chaired by the System Program Director (SPD), will control<br />
Level II requirements, changes which affect both Projects, changes that effect external interfaces, and any<br />
other that it deems necessary. The Deputy SPD is the designated alternate chairman. The Project<br />
Managers (PM) will chair the project CCB and control Level III (and below) changes. The deputy PMs<br />
are the designated alternate chairman.<br />
7.2 Program Documentation Library<br />
The <strong>GOES</strong> Documentation Library is the official point of receipt, storage and distribution for all project<br />
documentation associated with the <strong>GOES</strong> Program. All documentation is cataloged, controlled, and<br />
retained in a database management system. The library collection encompasses all types of media and<br />
employs various distribution methods. The NASA Work Instruction 415-WI-1410.1.1C (or its follow on)<br />
establishes the procedures for cataloging, controlling and disbursing <strong>GOES</strong>-R documentation.<br />