GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

GOES-R MANAGEMENT CONTROL PLAN (MCP)

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Identify Proposed<br />

Change<br />

(Start)<br />

Perform<br />

Analysis<br />

(technical)<br />

Needs further<br />

analysis<br />

Needs further<br />

analysis<br />

Contracts<br />

Negotiates<br />

(if applicable)<br />

No<br />

Draft<br />

CCR<br />

Form<br />

CM Reviews<br />

Assigns CCR#<br />

Engineering<br />

Review<br />

Board<br />

Valid?<br />

Yes<br />

Perform<br />

Analysis<br />

(cost, schedule, risk)<br />

Configuration<br />

Control Board<br />

Approved?<br />

Yes<br />

Effect<br />

Level I?<br />

Yes<br />

No<br />

No<br />

NESDIS<br />

RPSI<br />

CM Archives<br />

Request<br />

CM Archives<br />

Request<br />

Figure 18: Program Level Change Request Process (Level II)<br />

The change process is composed of three main components; the Engineering Review Board (ERB), the<br />

Configuration Control Board (CCB), and the Program Configuration Control Board (PCCB).<br />

Engineering Review Board (ERB): The Engineering Review Board determines the validity and necessity<br />

of proposed requirements changes and other contract applicable document (SOW, CDRL, and WBS)<br />

prior to their introduction into the formal CM process. The ERB will by chaired by the Systems<br />

Engineering Lead at the program or project level. At the project level, the ERB chairman may designate<br />

an alternate at his/her discretion. At the program level, either the Ground Segment Project Systems<br />

Engineering Lead or the Flight Project Systems Engineering Lead may be called upon as the acting ERB<br />

chairman in the absence of the Program Systems Engineering Lead. The chairman is responsible for<br />

inviting members of the engineering review board in accordance with the subject matter of the change.<br />

These members will finalize a technical impact analysis of the proposed change. The CCR may also be<br />

submitted to the Program/Project Control team for an initial cost and/or schedule impact analysis. If the<br />

change is validated, the ERB will provide its recommendation and impact study results to the<br />

Configuration Control Board (CCB).<br />

Configuration Control Board (CCB): The Configuration Control Board will review and consider the<br />

CCR and all analysis associated with it. CCB members will make a recommendation to the SPD or<br />

Project Managers, who are responsible for final disposition. If a CCR is approved, Contracts staff will be<br />

notified for their review for contractual implications.<br />

The Program CCB (PCCB): The PCCB is chaired by the System Program Director (SPD), will control<br />

Level II requirements, changes which affect both Projects, changes that effect external interfaces, and any<br />

other that it deems necessary. The Deputy SPD is the designated alternate chairman. The Project<br />

Managers (PM) will chair the project CCB and control Level III (and below) changes. The deputy PMs<br />

are the designated alternate chairman.<br />

7.2 Program Documentation Library<br />

The <strong>GOES</strong> Documentation Library is the official point of receipt, storage and distribution for all project<br />

documentation associated with the <strong>GOES</strong> Program. All documentation is cataloged, controlled, and<br />

retained in a database management system. The library collection encompasses all types of media and<br />

employs various distribution methods. The NASA Work Instruction 415-WI-1410.1.1C (or its follow on)<br />

establishes the procedures for cataloging, controlling and disbursing <strong>GOES</strong>-R documentation.<br />

Page 56 of 75