GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
GOES-R MANAGEMENT CONTROL PLAN (MCP)
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Milestone Type Key Milestones Critical Milestones Program Milestones Project<br />
Milestones<br />
Rebaseline<br />
DUS NESDIS <strong>GOES</strong>-R SPD Project Manager<br />
Approval Level<br />
Notification Level DOC DUS NESDIS SPD<br />
Baseline Date<br />
KDP I (DOC KDP<br />
C/D)<br />
KDP II<br />
Satellite ship<br />
Ground Block<br />
Delivery #1<br />
Mission Readiness<br />
Review<br />
Launch Readiness<br />
Date<br />
IOC – capable of<br />
delivering cloud<br />
and water vapor<br />
imagery<br />
KDP II KDP II Initial Baseline<br />
Review<br />
Initial ground System Instrument<br />
Delivery<br />
design reviews<br />
System SDR<br />
System PDR<br />
System CDR<br />
System Integration<br />
Readiness<br />
Flight Storage<br />
Readiness<br />
Instrument Delivery<br />
Mission Ops<br />
Readiness<br />
Flight Ops Readiness<br />
Interface Milestones<br />
Spacecraft and<br />
Ground Contract<br />
Award<br />
Ground Block<br />
Deliveries #2, #3, #4<br />
Spacecraft bus<br />
design review<br />
milestones<br />
Ground segment<br />
design review<br />
milestones<br />
Instrument<br />
Contract Award<br />
Spacecraft and<br />
Ground RFP<br />
release dates<br />
FOC – capable of<br />
delivering cloud<br />
and water vapor<br />
imagery from both<br />
east and west<br />
stations<br />
Figure 15: Description of Milestones in the <strong>GOES</strong>-R Program<br />
Milestones are baselined as noted in the table above. Baselined Program Master Schedule and Project<br />
Master Schedules will be maintained under formal configuration control. Schedules change, and the table<br />
above summarizes approval levels needed to change dates for program and project milestones.<br />
Projects may develop an internal schedule replan. An internal schedule replan is defined as a<br />
restructuring of the Level III schedule where all project requirements and scope remain the same,<br />
Program Level milestones are unaffected, schedule reserves are not reduced and the cost of the “to go”<br />
effort remains within project operating plan guidelines.<br />
If a baseline identified in the Program Master Schedule is no longer achievable a schedule “rebaseline”<br />
can be requested and approved at the levels defined below. If an individual milestone is projected to slip<br />
3 months or greater from the baseline dates established at IBR, notification of the appropriate level is<br />
required. Individual milestones delays with the potential to affect the program critical path will be<br />
reported regardless of the length of the schedule slip.<br />
Page 46 of 75