10.07.2015 Views

Fremantle Port Inner Harbour and Channel ... - Fremantle Ports

Fremantle Port Inner Harbour and Channel ... - Fremantle Ports

Fremantle Port Inner Harbour and Channel ... - Fremantle Ports

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Executive SummaryProject Status<strong>Fremantle</strong> <strong>Port</strong>s’ <strong>Inner</strong> <strong>Harbour</strong> Deepening Project (the Project) involved the dredging ofapproximately 3.1 million m 3 of consolidated <strong>and</strong> unconsolidated material using acombination of a Trailing Suction Hopper Dredge (TSHD) <strong>and</strong> a Cutter Suction Dredge (CSD).The dredged material was then used either to reclaim an area of seabed at Rous Head orplaced at an offshore spoil disposal area. The dredging was undertaken to deepen the DeepWater <strong>Channel</strong>, Entrance <strong>Channel</strong> <strong>and</strong> <strong>Inner</strong> <strong>Harbour</strong> to allow larger ships to utilise the<strong>Fremantle</strong> <strong>Inner</strong> <strong>Harbour</strong>.The dredging <strong>and</strong> reclamation works were undertaken in two phases. Phase 1 involved an11-week dredging program to remove s<strong>and</strong> from the <strong>Inner</strong> <strong>Harbour</strong>, Entrance <strong>Channel</strong> <strong>and</strong>Deep Water <strong>Channel</strong>, with all of the s<strong>and</strong> placed into reclamation at Rous Head. This initialphase of dredging <strong>and</strong> reclamation commenced on 6 January 2010 <strong>and</strong> was completed on21 March 2010. Phase 2 of dredging was undertaken over a 12-week period between9 August <strong>and</strong> 31 October 2010 <strong>and</strong> involved the removal of rock from the <strong>Inner</strong> <strong>Harbour</strong> <strong>and</strong>the Deep Water <strong>Channel</strong> <strong>and</strong> placement of this rock into the offshore disposal area. Phase 2included minor backhoe works carried out to remove a small amount of sediment(approximately 0.1% of the entire Project dredge volume) from some berth pockets of the<strong>Inner</strong> <strong>Harbour</strong> between 13 December 2010 to 7 January 2011, <strong>and</strong> 25 March to12 April 2011.All works were completed by 13 April 2011.This report - Purpose <strong>and</strong> ScopeAs a requirement of Ministerial Statement 801 (WA Minister for Environment, 18 August2009), a Compliance Assessment Plan (CAP) for the Project was prepared to the satisfactionof the Chief Executive Officer (CEO) of the Office of the Environmental Protection Authority(OEPA), including an agreed audit table. Utilising the CAP <strong>and</strong> audit table as a basis forassessment, this Compliance Assessment Report documents the compliance status since thecompletion of Project works, in accordance with Condition 4.6 of the MinisterialStatement 801. Previous Compliance Assessment Reports covered Phase 1 (Oceanica 2010b)<strong>and</strong> Phase 2 (Oceanica 2011) of Project works. Copies of the Compliance Assessment Plan<strong>and</strong> previous Compliance Assessment Reports can be found on <strong>Fremantle</strong> <strong>Port</strong>s website.It is noted that subsequent to approval of the CAP, <strong>Fremantle</strong> <strong>Port</strong>s received two separateapprovals under Section 45C of the Environmental Protection Act 1986 to: (i) re-orientate theoffshore disposal area; <strong>and</strong> (ii) amend the duration of dredging works from “20-26 weeks” to“up to 30 weeks in aggregate” to incorporate the period of minor backhoe works(EPA 2011a,b). The EPA considered that these changes would “not result in a significant,detrimental, environmental effect in addition to, or different from, the effect of the originalproposal” (EPA 2011b); such that the CAP remains a valid basis for compliance assessment.Compliance SummaryA summary of the compliance status of audit elements defined by the CAP are provided in thecompleted audit table of this report (Table 2.1). Few action items remain which are stillrelevant for compliance reporting during this monitoring period. Only one item requiredactive monitoring the "Annual survey footprint of the offshore disposal grounds" (801:M5.5).There were zero non-compliance issues with the conditions of Ministerial Statement 801during the post Project works period of August 2011 - August 2012.Oceanica: <strong>Fremantle</strong> <strong>Port</strong>s: <strong>Fremantle</strong> <strong>Port</strong> <strong>Inner</strong> <strong>Harbour</strong> <strong>and</strong> <strong>Channel</strong> Deepening, Compliance Assessment Report 2012iii

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!