13.07.2015 Views

Comparison of 9.5 mm SuperPave and Marshall Wearing I Mixes in ...

Comparison of 9.5 mm SuperPave and Marshall Wearing I Mixes in ...

Comparison of 9.5 mm SuperPave and Marshall Wearing I Mixes in ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

47was acceptable for both <strong>Marshall</strong> <strong>and</strong> Superpave mix designs at both medium <strong>and</strong> heavy trafficlevels.Asphalt contents were calculated for these mixtures us<strong>in</strong>g Equations 2.12 to 2.16. The asphaltcontent estimates calculated from these equations were consistently too high. Us<strong>in</strong>gexperience ga<strong>in</strong>ed after complet<strong>in</strong>g a few mix evaluations achieved better estimates than wereproduced with the equations.5.1.3 Specimen Fabrication <strong>and</strong> Test<strong>in</strong>gAs prescribed under <strong>Marshall</strong> mix design, test specimens were prepared over a range <strong>of</strong>different asphalt percentages to determ<strong>in</strong>e the optimum asphalt content. This range consists <strong>of</strong>½ percent <strong>in</strong>crements with two asphalt contents above <strong>and</strong> two below the estimated asphaltcontent. Also duplicate samples <strong>of</strong> each asphalt content were made. Two maximum specificgravity, or Rice, samples were also required at the estimated asphalt content accord<strong>in</strong>g toAASHTO T209, mak<strong>in</strong>g the total number <strong>of</strong> samples needed, 12 per mix design. Maximumspecific gravity test samples were not needed for all asphalt contents s<strong>in</strong>ce the <strong>Marshall</strong> methodallows for estimation <strong>of</strong> the maximum specific gravity <strong>of</strong> the other asphalt contents from theone measured value. Equations 2.1 to 2.10 are used for this analysis.Once the aggregates for the mixtures had been comb<strong>in</strong>ed for correct weight, they were heatedto the mix<strong>in</strong>g temperature <strong>of</strong> 162 C. A sufficient amount <strong>of</strong> PG 64-22 asphalt b<strong>in</strong>der was alsoheated to this temperature shortly before the mix<strong>in</strong>g process. The mix<strong>in</strong>g bowl <strong>and</strong> mix<strong>in</strong>gw<strong>and</strong> were also heated to the compaction temperature. Mix<strong>in</strong>g temperature was <strong>in</strong>dicated <strong>in</strong>the b<strong>in</strong>der evaluation data from the Citgo Asphalt Data Sheet. This evaluation sheet also<strong>in</strong>dicated that the compaction temperature was 149 C. In a separate oven, the compactionmolds were heated to the compaction temperature <strong>and</strong> the <strong>Marshall</strong> ha<strong>mm</strong>er was placed on ahotplate.The heated aggregate mixture was then placed <strong>in</strong>to the mix<strong>in</strong>g bowl <strong>and</strong> the required amount <strong>of</strong>asphalt b<strong>in</strong>der was added. This was i<strong>mm</strong>ediately placed <strong>in</strong> the tabletop mixer <strong>and</strong> mixed untilthe aggregate <strong>and</strong> b<strong>in</strong>der was thoroughly mixed. After mix<strong>in</strong>g, the entire specimen was placed<strong>in</strong> the mold, spaded 25 times with a spatula, <strong>and</strong> placed on the compaction pedestal. Thereta<strong>in</strong><strong>in</strong>g r<strong>in</strong>g was placed over the mold, the compaction ha<strong>mm</strong>er placed <strong>in</strong> the mold <strong>and</strong>attached to the automatic lift<strong>in</strong>g device. The lift<strong>in</strong>g device was then activated to apply theapplicable number <strong>of</strong> blows to the specimen. The correct number <strong>of</strong> blows per side for <strong>Marshall</strong>medium <strong>and</strong> heavy mixtures is 50 <strong>and</strong> 75, respectively. After the compaction to one side <strong>of</strong> thespecimen was complete, the mold was then flipped over <strong>and</strong> the compaction process repeatedfor the same amount <strong>of</strong> blows. Once the compaction process was complete, the sample <strong>and</strong>mold were removed <strong>and</strong> placed <strong>in</strong>to the specimen extraction device. The specimen wasremoved from the mold <strong>and</strong> allowed to cool. This entire process was repeated for the tenspecimens used for determ<strong>in</strong><strong>in</strong>g the optimum asphalt content.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!