6. Starting the Diesel Hammer<br />

6.6 Bringing the Diesel Pile Hammer and pile helmet into operating position<br />

Observe the operating instructions of the carrier equipment.<br />

Equipment to tie down any and all equipment being transported shall be provided by the transport company<br />

and be of such to prevent movement of equipment or damage. PPE (Personal Protective Equipment) that<br />

is required to perform any and all work shall be provided by your employer to safely perform this task. Make<br />

sure to read 1926.106 (a) (b) (c) (d) when working over or near water.<br />

6.6.1 Placing the Diesel Hammer in swinging lead – lead laying on the ground<br />

• Diesel Pile Hammers up to the D62 can be equipped with channel guiding<br />

• The hammer must be slid in the lead from one side<br />

• Before raising up the lead the starting device and the hammer lifting ears must be connected to the<br />

crane hoist line<br />

6.6.2 Placing the Diesel Hammer in an offshore lead – lead laying on the ground<br />

• When setting the hammer into the lead pay particular attention to slide the lead guiding carrier and the<br />

hammer complete to the guiding bell to prevent uncontrolled sliding when raising the hammer and lead<br />

system to upright position<br />

• After setting the hammer into the lead the backside guiding brackets must be bolted on<br />

111 Berry Road<br />

Houston, TX 77002<br />

Tel. (713) 691-3000<br />

Fax (713) 691-0089<br />

E-mail: info@bauerpileco.com<br />

www.bauerpileco.com<br />

<strong>Operations</strong> <strong>Manual</strong> December 2012<br />

36