8. Shutting down and storage<br />
3. Install the piston locking screws, impact block<br />
clamp, protective cap and exhaust covers<br />
(See Chapter 4.1 “Transport safety”).<br />
4. Remove the ropes from the fuel control pump.<br />
5. Take the hammer out of the lead. Put the<br />
hammer aside in reverse procedure like<br />
described in chapter 6.5.<br />
7. Remove the wire rope slings from the lifting<br />
ears (3).<br />
8. Put the carrier equipment out of operation<br />
(See operating instructions for the carrier<br />
equipment).<br />
9. Secure the job site in accordance with local<br />
regulations for barricaded job sites.<br />
6. Set the hammer on stable ground, if necessary<br />
use 3” thick wood planks.<br />
111 Berry Road<br />
Houston, TX 77002<br />
Tel. (713) 691-3000<br />
Fax (713) 691-0089<br />
E-mail: info@bauerpileco.com<br />
www.bauerpileco.com<br />
<strong>Operations</strong> <strong>Manual</strong> December 2012<br />
53