AGENDA ITEM<br />
<strong>Chaffey</strong> Community <strong>College</strong> District<br />
GOVERNING BOARD<br />
<strong>TO</strong>PIC FONTANA PARKING LOT PROJECT – FUNDING SOURCES APPROVAL<br />
Communication No. IV.F.3.k<br />
SUPPORTS BOARD ENDS STATEMENT/POLICY<br />
June 26, 2008<br />
<strong>Board</strong> Meeting Date<br />
This action is supported by Ends Statement 8.4: Provide appropriate fiscal strategies to address growth<br />
and other external environmental factors.<br />
PROPOSAL<br />
To transfer $1,022,321 from the bond program reserve and authorize use of approximately $2,737,679 of<br />
bond interest earned for the Fontana Parking Lot Project budget.<br />
BACKGROUND<br />
A necessary part of the Fontana Building, Phase III Project is the construction of a parking lot. The<br />
funding for the Fontana parking lot is not included in the Fontana Building, Phase III budget. The<br />
estimated budget for this project is $3,760,000. It is recommended that the funding sources for this<br />
project be the bond fund program reserve and bond fund interest earned.<br />
BUDGET IMPLICATIONS<br />
Funding Source – Bond fund program reserves and bond fund interest earned.<br />
Status of Funds – Funds of $1,022,321from the bond fund program reserves will be transferred, and<br />
$2,737,679 from bond fund interest earned will be authorized to be used for the Fontana Parking Lot<br />
Project budget. In the 2007–2008 fiscal year, $50,000 of this will be transferred for anticipated currentyear<br />
expenses.<br />
Future Implications – The remaining balance of the Fontana parking lot budget will be included in the<br />
2008–2009 adopted bond fund budget.<br />
RECOMMENDATION<br />
To transfer $1,022,321 from the bond fund program reserve and authorize use of approximately<br />
$2,737,679 of bond fund interest earned for the Fontana Parking Lot Project budget.<br />
Prepared by: Anita D. Undercoffer, Director, Budgeting Services/Disbursing Officer<br />
Submitted by: C. Earl Davis, Vice President, Business Services<br />
Recommended by: Henry D. Shannon, Superintendent/President<br />
51 6/26/08 Regular <strong>Board</strong> Meeting