In addition to regular scheduled inspections, structures should be inspected<br />

after severe storm events.<br />

Inspection records<br />

The inspection record <strong>of</strong> a bridge or major culvert must include all <strong>of</strong> the<br />

following:<br />

• date <strong>of</strong> the inspection<br />

• a condition assessment <strong>of</strong> the components <strong>of</strong> the structure<br />

• a recommendation for any repairs that may be required and a schedule<br />

for those repairs<br />

• the date <strong>of</strong> the next scheduled inspection<br />

• the length <strong>of</strong> time a bridge has been at its current site<br />

• a note about whether a bridge was designed and constructed to be at the<br />

current site for no more than 15 years.<br />

Inspection records for major bridges and culverts must be retained for 1 year<br />

beyond the actual life <strong>of</strong> the structure at the site. Should a structure fail, these<br />

records will be useful in any subsequent investigation. These records can also<br />

be used as a reference to determine the type <strong>of</strong> structures that are costeffective<br />

and environmentally suitable for similar stream crossings.<br />

Structural deficiencies noted in inspections<br />

The sequence <strong>of</strong> identifying and correcting structural deficiencies in existing<br />

bridges is as follows:<br />

1. A qualified inspector identifies and records possible structural<br />

deficiencies.<br />

2. A pr<strong>of</strong>essional engineer carries out a field review <strong>of</strong> the structure, and<br />

confirms or recommends the following, as applicable:<br />

• the types <strong>of</strong> work that must be carried out to correct the deficiencies,<br />

or<br />

• the need to protect road users by either<br />

– installing signs detailing the load rating prepared by the engineer,<br />

or<br />

– closing or removing the structure.<br />

<strong>Road</strong> prism maintenance<br />

Maintenance is required to ensure user safety and stability <strong>of</strong> the road prism,<br />

and to minimize sediment transport from the road prism.<br />