Is it necessary to install a downhole safety valve in a subsea ... - NTNU
Is it necessary to install a downhole safety valve in a subsea ... - NTNU
Is it necessary to install a downhole safety valve in a subsea ... - NTNU
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Is</strong> <strong>it</strong> <strong>necessary</strong> <strong>to</strong> <strong><strong>in</strong>stall</strong> a <strong>downhole</strong> <strong>safety</strong> <strong>valve</strong> <strong>in</strong> a <strong>subsea</strong> oil/gas well?<br />
Prepare for runn<strong>in</strong>g completion.<br />
Make up 7” double and rack back same.<br />
Make up and run bot<strong>to</strong>m of tub<strong>in</strong>g completion assemblies.<br />
Run tub<strong>in</strong>g <strong>to</strong> DHSV depth.<br />
Run <strong>in</strong> hole production PBR on drill pipe for space-out.<br />
Close BOP and mark drill pipe.<br />
Pull drill pipe out of hole.<br />
Make up DHSV assembly.<br />
Test control l<strong>in</strong>es.<br />
Run rema<strong>in</strong><strong>in</strong>g tub<strong>in</strong>g accessory <strong>to</strong> f<strong>in</strong>al space out<br />
9) Run tub<strong>in</strong>g hanger<br />
Make up tub<strong>in</strong>g hanger <strong>to</strong> tub<strong>in</strong>g.<br />
Connect control l<strong>in</strong>es <strong>to</strong> tub<strong>in</strong>g hanger. Install tub<strong>in</strong>g hanger <strong>in</strong> center.<br />
Make up tub<strong>in</strong>g hanger runn<strong>in</strong>g <strong>to</strong>ol <strong>to</strong> tub<strong>in</strong>g hanger<br />
Run tub<strong>in</strong>g hanger on drill pipe.<br />
Land and lock tub<strong>in</strong>g hanger <strong>to</strong> the x-mas tree.<br />
Open <strong>downhole</strong> supply <strong>valve</strong>s DS1-DS4.<br />
Engage electric stab and hydraulic system.<br />
Close middle pipe ram.<br />
Pressure test tub<strong>in</strong>g hanger gallery seals, DHSV control l<strong>in</strong>es and tub<strong>in</strong>g hanger.<br />
Spot high viscos<strong>it</strong>y mud across tub<strong>in</strong>g hanger.<br />
Unlatch tub<strong>in</strong>g hanger runn<strong>in</strong>g <strong>to</strong>ol. Pull out of hole w<strong>it</strong>h tub<strong>in</strong>g hanger runn<strong>in</strong>g <strong>to</strong>ol on<br />
drill pipe.<br />
10) Pull tub<strong>in</strong>g hanger isolation sleeve<br />
Pull tub<strong>in</strong>g hanger isolation sleeve on 0.125” slick l<strong>in</strong>e through the mar<strong>in</strong>e riser.<br />
11) Run workover riser<br />
Run tree cap, tree cap runn<strong>in</strong>g <strong>to</strong>ol, electric stab assembly, workover riser and surface<br />
tree w/45 ft bails<br />
Land and lock tree cap.<br />
12) Set prod packer<br />
Displace well <strong>to</strong> diesel, drop ball <strong>to</strong> seal off tub<strong>in</strong>g side.<br />
Pressure up tub<strong>in</strong>g <strong>to</strong> set production packer<br />
Inflow test DHSV. Test production packer. Function test LBV and OBV<br />
13) Pull Pre <strong><strong>in</strong>stall</strong>ed production packer<br />
Rig up wire l<strong>in</strong>e and run <strong>in</strong> hole. Pull pre-<strong><strong>in</strong>stall</strong>ed production packer sett<strong>in</strong>g plug<br />
14) Flow well<br />
Flow well <strong>to</strong> test plant.<br />
Rig up wirel<strong>in</strong>e production logg<strong>in</strong>g <strong>to</strong>ol.<br />
Log and flow well.<br />
15) Test and abandonment of well<br />
Shut <strong>in</strong> and <strong>in</strong>flow test DHSV.<br />
Pump MEG on <strong>to</strong>p of DHSV<br />
Rig up tub<strong>in</strong>g hanger crown plug.<br />
Diploma thesis, <strong>NTNU</strong> 2002<br />
40