<strong>MANUAL</strong> 4 – BITUMINOUS PAVEMENT SEALS<br />
2.8 Training of spray equipment operators and team<br />
2.8.1 Uniformity<br />
Before attempting any bituminous surfacing, it is recommended that the spray operators and<br />
team be introduced to the spray operation by first spraying water at a uniform application<br />
per square metre. Until the operator and team are fully conversant with all aspects of the<br />
operation and confident in applying a uniform application of water, spraying of diluted<br />
emulsion must not be attempted.<br />
The operations include:<br />
• Initiating the burners.<br />
• Starting the spray machine.<br />
• Checking the delivery of the pump.<br />
• Practicing the movement of the protective screens while spraying.<br />
• Practicing initiating of the spraying by the stopwatch operator.<br />
• Checking the rate of application for 2 m; 3 m and 4 m control sections.<br />
• Practicing keeping the spray lance at a uniform height above the surface to be covered<br />
while spraying.<br />
• Recording the results of the times and dipstick readings.<br />
Once the unit is comfortable in all the phases/aspects of the spray operation, the next step<br />
is to apply the diluted 1:10 emulsion on the section of road to be surfaced. At the same<br />
time, the use of the protective screens (see Photo 4.2) to protect any concrete works, such<br />
as kerbing, channelling, etc. must be introduced, and the labour trained in the systematic<br />
moving of the screens along the edge of the area to be surfaced. (For a clean operation this<br />
is essential.) The screens must move slightly ahead of the binder application.<br />
Photo 4.2: Spraying using protective screens and reinforced paper<br />
IMPLEMENTING EMPLOYMENT INTENSIVE ROAD WORKS 18