<strong>MANUAL</strong> 4 – BITUMINOUS PAVEMENT SEALS<br />
Where the binder is applied by a motorised hand sprayer, one Chippy will be sufficient.<br />
Photo 4.12<br />
The aggregate is loaded into the Chippy by wheelbarrows (± 66 litres) and the Chippy guided<br />
along the length of the road in accordance with the manufacturer’s instructions.<br />
Using a hand sprayer and one Chippy, the procedure illustrated in Figure 4.6 is recommended<br />
for applying the aggregate using 2 3 105 litre drums at the calculated spacing.<br />
Figure 4.6: Procedure for applying aggregate<br />
Once sufficient stone has been applied and one can walk on the surface without coming into<br />
contact with the wet binder, the bare spaces can be filled with more stone. The aggregate<br />
must be placed shoulder to shoulder. However, care must be taken not to have double layers<br />
of stone.<br />
Gently broom the surface to distribute any loose stone that may be forming double layers.<br />
The better this process is done, the better and more efficient the seal will be.<br />
Once the surface has been covered with the aggregate, without bare patches of binder<br />
showing, rolling with the pedestrian roller can commence.<br />