<strong>MANUAL</strong> 4 – BITUMINOUS PAVEMENT SEALS<br />

Where the binder is applied by a motorised hand sprayer, one Chippy will be sufficient.<br />

Photo 4.12<br />

The aggregate is loaded into the Chippy by wheelbarrows (± 66 litres) and the Chippy guided<br />

along the length of the road in accordance with the manufacturer’s instructions.<br />

Using a hand sprayer and one Chippy, the procedure illustrated in Figure 4.6 is recommended<br />

for applying the aggregate using 2 3 105 litre drums at the calculated spacing.<br />

Figure 4.6: Procedure for applying aggregate<br />

Once sufficient stone has been applied and one can walk on the surface without coming into<br />

contact with the wet binder, the bare spaces can be filled with more stone. The aggregate<br />

must be placed shoulder to shoulder. However, care must be taken not to have double layers<br />

of stone.<br />

Gently broom the surface to distribute any loose stone that may be forming double layers.<br />

The better this process is done, the better and more efficient the seal will be.<br />

Once the surface has been covered with the aggregate, without bare patches of binder<br />

showing, rolling with the pedestrian roller can commence.<br />

IMPLEMENTING EMPLOYMENT INTENSIVE ROAD WORKS 29<br />

MODULE<br />

1<br />

2<br />

3<br />

4<br />

5<br />

6<br />

7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!