<strong>MANUAL</strong> 4 – BITUMINOUS PAVEMENT SEALS<br />
Figure 4.5: Sketch of spray screen (Refer to Workshop drawing LIC 007)<br />
4. <strong>Construction</strong><br />
4.1 Preparation of surface<br />
• Sweep the road clean. All loose material and mud that has been brought onto the<br />
surface by traffic must be removed.<br />
• Stake out width of road to be surfaced, marking out the edge of the road with a 7 mm<br />
sisal rope.<br />
• If necessary, lightly spray the surface with a diluted 1:8 emulsion (1 litre emulsion to 8<br />
litres water). Normally with an ETB, this should only be necessary if the ETB has been<br />
exposed to traffic for an extended period. This application of emulsion and water<br />
could be regarded as lightly priming the ETB (0,5 – 0,6 litres/m 2 of diluted Anionic<br />
stable-grade emulsion should be applied).<br />
• Protect any kerbs and drains, etc. from the emulsion spray. (Photo 4.7)<br />
• Use reinforced paper for the construction joints at the beginning and end of each<br />
spray. (Photo 4.8)<br />