A Feasibility Study - Aaltodoc - Aalto-yliopisto
A Feasibility Study - Aaltodoc - Aalto-yliopisto
A Feasibility Study - Aaltodoc - Aalto-yliopisto
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
The permeate production on Site 2 is fairly stable all through the calculated design<br />
points, between 500 and 700 m³/day. The permeate production peaks at 683 m³/day<br />
when the nominal pump capacity is 0,15 m³/s and the load factor 0,62. The load factor is<br />
steadily decreasing all through the calculated area, which expresses that Site 2 is not<br />
well suited to the <strong>Aalto</strong>RO system. The permeate production of Site 2 is presented in<br />
Figure 44.<br />
Permeate (m³/day)<br />
800<br />
700<br />
600<br />
500<br />
400<br />
300<br />
200<br />
100<br />
0<br />
Permeate (m³/day)<br />
Load factor (%)<br />
0<br />
0 0,05 0,1 0,15 0,2 0,25 0,3<br />
WaveRoller nominal pump capacity (m³/s)<br />
Figure 44. Permeate production (m³/day) and load factor on Site 2.<br />
The cost of water is presented in Figure 45. The minimum cost of water in Site 2 is 1,58<br />
€/m³ with a nominal pump capacity of 0,03 m³/s and of a load factor of 1. The load<br />
factor of 1 signifies that all the wave power that the WaveRoller is able to utilize is<br />
suitable for the RO membranes. After this point the load factor drops quickly, while the<br />
permeate production grows only slightly and the costs increase steadily. Therefore the<br />
minimum cost of water is achieved with the smallest calculated nominal pump capacity.<br />
62<br />
1,2<br />
1<br />
0,8<br />
0,6<br />
0,4<br />
0,2<br />
Load factor