order and will be installed also in this area. Carpeting is scheduled to be<br />
applied in this area by the end <strong>of</strong> this month.<br />
This is the northeast corner <strong>of</strong> the library. Wooden shelving<br />
and library furniture have been ordered. We expect summer delivery and<br />
installation.<br />
Next slide, please. This is the main kitchen area. The<br />
ventilation hood is the hanging structure in the center. Ranges, ovens,<br />
steam kettles and et cetera will be installed in this area this summer. This<br />
week, quarry tile is being laid on the floor.<br />
Furniture and equipment are shown on the financial slide with<br />
a current budget <strong>of</strong> just under $4 million, and the existing balance at three<br />
million two. This slide represents the plan for furnishing the final parts <strong>of</strong><br />
this project. The furniture and equipment and technology ordered and<br />
planned to be ordered are within the established budget for these items.<br />
Safety on the job is an important item; TLT and Gilbane are<br />
actively overseeing. Since the last report, there were two accidents. One<br />
was an ankle sprain and the other was a hammer accident. Both men are<br />
back at work. We use Briggs Engineering to test the various products and<br />
systems. Weekly visits by the Building Department have proved very<br />
helpful in keeping Phase 2 on track and in compliance with regulations.<br />
We have had three visits from the Massachusetts School Building<br />
Authority during Phase 2 and a fourth visit is scheduled for this<br />
Tinkham Reporting<br />
(508) 759-9162<br />
1-<br />
23