B.S. SPONGE PRIVATE LIMITED<br />
Village: Taraimal, Tehsil: Gharghoda, District: Raigarh, (C.G.)<br />
REIA Report for the Proposed Mini Integrated Steel Plant<br />
Chapter – 10<br />
10.2.7. RAINWATER HARVESTING (TOR # 24)<br />
Rainwater harvesting structures will be constructed to harvest the run-off water from roof<br />
tops by laying a separate storm water drainage system for recharging of ground water.<br />
4 nos. of rain water harvesting structures each of size 10m x 5m x 1.5 m will be provided<br />
in the plant to recharge the precious ground water. Rain harvesting pits are being<br />
constructed as per guidelines of State Ground Water Board.<br />
10.3 POST PROJECT MONITORING STRATEGY<br />
The monitoring of various environmental parameters is necessary which is part of the<br />
environmental protection measures. Monitoring is an important feature because the<br />
efficiency of control measures can only be determined by monitoring. A comprehensive<br />
monitoring programme is given under.<br />
Locations and frequency of monitoring as per the guidelines of CECB and MOEF are<br />
tabulated below.<br />
MONITORING SCHEDULE FOR ENVIRONMENTAL<br />
PARAMETERS<br />
S. No. Particulars Frequency of<br />
Monitoring<br />
1. Water & Waste water<br />
quality<br />
A. Water quality in the<br />
area<br />
Once in a month<br />
except for heavy<br />
metals which will be<br />
monitored on quarterly<br />
basis.<br />
2. Air Quality<br />
A. Stack Monitoring Online monitors<br />
(major stacks)<br />
Duration of<br />
sampling<br />
Composite<br />
sampling<br />
(24 hourly)<br />
Parameters required to<br />
be monitored<br />
As per IS: 10500<br />
Once in a month<br />
SO 2 & NO x<br />
B. Ambient Air quality Twice a week 24 hours RSPM, SPM,<br />
continuously SO 2 & NO x<br />
C. Fugitive emissions Once in three 8 hourly Particulate matter<br />
months<br />
3. Meteorological Data<br />
Meteorological data to be Daily<br />
Continuous Temperature, RH, rainfall,<br />
monitored at the plant.<br />
monitoring wind direction & speed.<br />
PIONEER ENVIRO 10- 21 <strong>Environment</strong>al Impact Assessment Report<br />
Laboratories & Consultants Pvt. Ltd.<br />
SPM