B.S. SPONGE PRIVATE LIMITED<br />
Village: Taraimal, Tehsil: Gharghoda, District: Raigarh, (C.G.)<br />
REIA Report for the Proposed Mini Integrated Steel Plant<br />
Chapter – 2<br />
The alloy cake from C.I. Pan is removed and broken manually with hammer to required<br />
lump size.<br />
The slag produced in the process, generally free from metal, after cooling is removed by<br />
lorry to the slag dump.<br />
2.5.5.5 POWER GENERATION: (TOR # 21)<br />
Waste Heat Recovery Boilers will be installed behind the ABC of DRI kiln in bypass<br />
configuration. The flue gases after ABC will be taken to unifired furnace chamber and<br />
then flow over banks of super heater, convective evaporator and economizer before being<br />
discharged to atmosphere through ESP, ID fan and stack. 12 MW electricity will be<br />
generated from WHRB. In the Fluidized Bed Combustion boiler envisaged, combustion<br />
of fuel particles is achieved in suspension with an inert aggregate i.e. sand. Combustion<br />
air will be fed through air nozzles from underneath into the sand fuel bed. Oil burner will<br />
be provided for start up and low load flame stabilization. The fuels proposed in FBC<br />
Boiler are Char & Coal. The flue gases will pass over various heat transfer surfaces to<br />
ESP and then finally discharged through ID fan and stack. 36 MW of Power generation<br />
proposed through FBC Boiler.<br />
The condensate after condenser of STG will be pumped to a common deaerator by<br />
condensate extraction pumps. Feed water from the deaerator will be pumped to the waste<br />
heat recovery boiler as well as FBC boiler by boiler feed pumps.<br />
The steam generated from both the WHRB and FBC boilers will drive the steam turbine<br />
through a common steam header to generate 48 MW of Electricity. The power generated<br />
will be used for captive consumption.<br />
Process flow diagram is shown as figure 2.1.<br />
PIONEER ENVIRO 2 - 18 <strong>Environment</strong>al Impact Assessment Report<br />
Laboratories & Consultants Pvt. Ltd.