Construction - Clearwater - 5 MGD Brackish <strong>Florida</strong>n Aquifer RO System<br />
Critical Project Milestones<br />
Projected<br />
Amended<br />
Actual<br />
Phase 1 Pilot Testing and Preliminary Design 11/30/2010 01/31/2012 01/31/2012<br />
Phase 2 Concentrate Injection Well 09/30/2011 12/31/2015<br />
Phase 5 Treatment Plant Design and Permitting 01/31/2013<br />
Phase 3 Wellfield Engineering Design and <strong>Water</strong> Use<br />
12/31/2013 05/31/2012<br />
Permitting<br />
Phase 4 Wellfield Construction 12/31/2014 05/31/2014<br />
Phase 7 Engineering Construction Services 05/31/2015<br />
Phase 6 Plant Construction 05/31/2015<br />
Construction finished/ certified 12/31/2015<br />
Project Complete/ Funding Agreement Expires 12/31/2016<br />
Status As Of February 28, 2012<br />
The well driller for the exploratory stage of the concentration injection well project began work on January 30, 2012, and is<br />
scheduled to be completed in June 2012. The exploratory test well program is nearing completion. Most sites have been tested<br />
and reports finalized. The City of Clearwater and FDEP have reviewed the Preliminary Design Report (PDR), and the PDR is in the<br />
process of being finalized. The RO2 impact analysis groundwater modeling has been completed and is being reviewed for use<br />
with the <strong>Water</strong> Use Permit (WUP) that will be submitted to the <strong>District</strong>. The 60 percent design plans are being prepared for the<br />
RO2 plant site, well heads, and raw water pipelines. A public meeting has been scheduled for the RO2 plant site for April 3, 2012.<br />