Design & Construction - Plant City Sydney and Park Road Transmission<br />
and Pumping<br />
Critical Project Milestones<br />
Projected<br />
Amended<br />
Actual<br />
Notice to Proceed 01/15/2008 03/10/2009<br />
Basin Board Notification 02/01/2008 06/04/2009<br />
Draft Agreement to Contract Administration 09/30/2008 11/19/2008<br />
Draft Agreement returned from Contracts Administration 10/31/2008 12/09/2008<br />
Contract Executed 01/01/2009 03/09/2008<br />
Design Commence 03/31/2009 04/07/2009<br />
Construction Commence-Sydney Road 10/31/2010 02/28/2012<br />
Construction Complete-Sydney Road 07/31/2011 02/28/2013<br />
Contract Termination 12/31/2012 12/31/2014<br />
Construction Commence-Park Rd. 05/30/2013<br />
Construction Complete-Park Rd. 05/30/2014<br />
Status As Of February 29, 2012<br />
In December 2008, the service agreement with the Walden Lake golf course was signed, and the cooperative funding agreement<br />
was executed on March 9, 2009. The City began the project design with the consultant on April 7, 2009, and has completed design<br />
plans and specifications. In August 2010, the City requested a 6 month time extension of the dates for construction. The City<br />
needed additional time to obtain railroad crossing agreements and additional easements for construction. The time extension did<br />
not affect the contract termination date, and a response letter was sent to the City on September 7, 2010, approving this request. In<br />
March 2011, the City informed the <strong>District</strong> that the Walden Lake Golf Course filed chapter 11 bankruptcy, which involves<br />
reorganizing finances. The golf course plans to continue operating through the process and the City is confident that the golf<br />
course will continue to be a viable option. The City is currently identifying additional customers along the proposed reclaimed<br />
line's route that could beneficially use the reclaimed water in lieu of the golf course. ACTION TO DATE: In July 2011, the Governing<br />
Board approved staff recommendation to amend the existing agreement to: upsize the Sydney Road line from 18" to 24", extend<br />
the termination date from December 31, 2012 to December 31, 2014, the addition of the Park Road transmission line to serve<br />
additional customers, and increase the <strong>District</strong> funding contribution by $1,005,000, for a total project cost of $6,126,000. The first<br />
amendment was executed on February 2, 2012. The City revised and updated the bid documents for the Sydney Road line and the<br />
project was advertised on December 30, 2011. Bids have been received for the Sydney Road line and are being evaluated. The<br />
City plans to begin construction on the Sydney Road line by March 12, 2012, and the Park Road line by May 30, 2013.<br />